Valid

GB 16889-2024Standard for pollution control on the landfill site of municipal solid waste (English PDF)

生活垃圾填埋场污染控制标准

Preview PDF

This is a limited preview

Buy now to download the full PDF (17 pages)

Need quotation for your management?

Get a formal quotation for GB 16889-2024 in 30 minutes.

Issued by

MEE; SAMR

Level / Type

National · Mandatory

Issue date

July 23, 2024

Implementation date

September 1, 2024

Scope

GB 16889-2024 is the English-translated version of 生活垃圾填埋场污染控制标准.

GB 16889-2024 sets the environmental protection requirements for municipal solid waste landfills: site selection, design, construction and acceptance, waste acceptance, operation, closure and post-closure maintenance and management, pollutant discharge control, monitoring, and implementation and supervision.

It applies to the construction, operation, closure and post-closure management of new landfills and to the issue of pollutant discharge permits, and to the operation, closure and post-closure management of existing landfills.

Issued on 23 July 2024 by the Ministry of Ecology and Environment and the State Administration for Market Regulation, in force since 1 September 2024, it replaces GB 16889-2008.

Found what you need?

Document preview — GB 16889-2024

National Standard of the People's Republic of China

ICS
13.030.10
Classification
Z 71
Replacing
GB 16889-2008

Issued by: Ministry of Ecology and Environment; State Administration for Market Regulation

Contents

  • Foreword3
  • 1 Scope4
  • 2 Normative references4
  • 3 Terms and definitions6
  • 4 Site selection requirements7
  • 5 Design, construction and acceptance requirements7
  • 6 Requirements for wastes accepted for landfill9
  • 7 Operation requirements10
  • 8 Closure and post-closure maintenance and management requirements11
  • 9 Pollutant discharge control requirements11
  • 10 Monitoring requirements14
  • 11 Implementation and supervision17

Foreword

This standard is formulated to implement the Environmental Protection Law, the Law on the Prevention and Control of Environmental Pollution by Solid Wastes, the Soil Pollution Prevention and Control Law, the Water Pollution Prevention and Control Law and the Atmospheric Pollution Prevention and Control Law of the People's Republic of China, the Regulations on Groundwater Management and the Regulations on the Administration of Pollutant Discharge Permits; to prevent and control environmental pollution, improve the quality of the ecological environment, and promote the sorting of municipal solid waste and progress in landfill technology.

This standard specifies the environmental protection requirements for municipal solid waste landfills covering site selection, design, construction and acceptance, waste acceptance, operation, closure and post-closure maintenance and management, pollutant discharge control, monitoring, and implementation and supervision.

This standard was first issued in 1997 and first revised in 2008; this is the second revision.

The main changes in this revision are:

- the design and construction requirements for the basic facilities of landfills have been improved;

- low-carbon operation requirements for methane utilisation and emission reduction at landfills have been added;

- the technical requirements for sending leachate to centralised wastewater treatment facilities have been adjusted;

- the management requirements for landfilling fly ash from municipal solid waste incineration have been clarified;

- the pollution control requirements during operation, closure and post-closure maintenance and management have been detailed;

- technical requirements for the development and use of landfill land have been added.

The pollutant discharge limits specified in this standard are basic requirements. Provincial people's governments may set local discharge standards for items not specified here, and stricter local standards for items that are.

This standard was organised by the Department of Solid Waste and Chemicals and the Department of Regulations and Standards of the Ministry of Ecology and Environment. Main drafting organisations: Chinese Research Academy of Environmental Sciences, Tongji University, Tsinghua University, China Urban Construction Design and Research Institute Co., Ltd., and China University of Mining and Technology (Beijing).

This standard was approved by the Ministry of Ecology and Environment on 23 July 2024 and is interpreted by it. It has been in force since 1 September 2024, from which date GB 16889-2008, Standard for pollution control on the landfill site of municipal solid waste, is repealed.

1 Scope

This standard specifies the environmental protection requirements for municipal solid waste landfills covering site selection, design, construction and acceptance, waste acceptance, operation, closure and post-closure maintenance and management, pollutant discharge control, monitoring, and implementation and supervision.

This standard applies to pollution control and supervision during the construction, operation, closure and post-closure maintenance and management of new municipal solid waste landfills, and to the issue of pollutant discharge permits. It also applies to pollution control and supervision during the operation, closure and post-closure maintenance and management of existing landfills.

2 Normative references

This standard cites the following documents or clauses thereof. For dated references, only the edition cited applies. For undated references, the latest edition, including all amendments, applies.

Water quality methods: GB 7466, GB 7467, GB 7469, GB 7470, GB 7471, GB 7472, GB 7475, GB 7485, GB 11893, GB 11901, HJ/T 59, HJ/T 70, HJ/T 132, HJ 195, HJ 199, HJ/T 341, HJ 347.1, HJ 347.2, HJ/T 399, HJ 485, HJ 486, HJ 505, HJ 535, HJ 536, HJ 537, HJ 597, HJ 636, HJ 665 to HJ 671, HJ 694, HJ 700, HJ 757, HJ 776, HJ 828, HJ 908, HJ 1001 and HJ 1182.

Solid waste methods: GB/T 15555.1, GB/T 15555.3, GB/T 15555.4, GB/T 15555.5, GB/T 15555.7, GB/T 15555.10, HJ/T 300, HJ 687, HJ 702, HJ 749, HJ 750, HJ 751, HJ 752, HJ 766, HJ 767, HJ 781, HJ 786 and HJ 787.

Emissions, monitoring and site investigation: GB 13486 Portable thermocatalytic methane detector and alarm; GB 14554 Emission standards for odour pollutants; GB 16297 Integrated emission standard of air pollutants; GB/T 18772 Technical requirements for environmental monitoring of sanitary landfill sites for municipal solid waste; HJ 25.1, HJ 25.2 and HJ 25.3 on soil contamination investigation, risk control and risk assessment of construction land; HJ 91.1 Technical specification for wastewater monitoring; HJ 164 Technical specifications for groundwater environmental monitoring; HJ 604 total hydrocarbons, methane and non-methane hydrocarbons in ambient air; HJ 819 Self-monitoring technology guidelines for pollutant sources, general rules; HJ 905 Technical specification for odour pollution monitoring; HJ 1134 Technical specification for pollution control of fly ash from municipal solid waste incineration.

Engineering: GB/T 23485 Disposal of sludge from municipal wastewater treatment plant, quality of sludge for co-landfilling; GB/T 25179 Technical requirements for utilisation of stabilised landfill sites; GB/T 50123 Standard for geotechnical testing method; GB 50869 Technical code for municipal solid waste sanitary landfill; GB 51220 Technical code for closure of municipal solid waste sanitary landfill; CJJ 113 Technical code for liner systems of municipal solid waste sanitary landfill; CJJ 133 Technical code for landfill gas collection, treatment and utilisation; CJJ 176 Technical code for geotechnical engineering of municipal solid waste sanitary landfill; CJJ/T 214 Technical specification for leak location of geomembrane liners; CJ/T 234 High density polyethylene geomembrane for landfills.

Regulations: Regulations on the Administration of Pollutant Discharge Permits (State Council Decree No. 736); Measures for the Administration of Automatic Monitoring of Pollution Sources (SEPA Order No. 28); Measures for the Administration of Environmental Monitoring (SEPA Order No. 39).

3 Terms and definitions

The following terms and definitions apply to this standard.

3.1 municipal solid waste

Solid waste generated in daily life or in activities providing services for daily life, and solid waste deemed to be municipal solid waste by laws and administrative regulations.

3.2 municipal solid waste landfill site

A facility for the landfill disposal of municipal solid waste composed of a number of disposal cells and structures. Landfill in this standard always means a municipal solid waste landfill.

3.3 liner

A layer of natural and/or synthetic materials placed at the bottom and on the side slopes of a landfill to prevent pollution by seepage.

3.4 natural foundation layer

The foundation layer below the liner, consisting of undisturbed soil.

3.5 natural clay liner

A liner formed by mechanically compacting treated natural clay.

3.6 single composite liner system

A liner consisting of one synthetic material liner and a clay liner.

3.7 double composite liner system

A liner consisting of two synthetic material liners and a clay liner.

3.8 independent landfill partitioning

An independent landfill cell with its own leachate collection and drainage system, isolated from municipal solid waste.

3.9 equalization basin

A structure placed ahead of the leachate treatment system that equalises and stores leachate, or also pre-treats it.

3.10 operation period

The period during which landfilling is carried out.

3.11 maintenance and management period after landfill closure

The period after closure during which maintenance, pollution control and environmental management continue until the landfill has stabilised.

3.12 existing municipal solid waste landfill

A landfill built and in operation, or whose environmental impact assessment was approved, before the date this standard came into force.

3.13 new-built municipal solid waste landfill

A new, rebuilt or extended landfill whose environmental impact assessment is approved from the date this standard came into force.

4 Site selection requirements

4.1 The landfill site shall comply with ecological and environmental protection laws and regulations and with zoning-based environmental control, overall urban and rural planning and special sanitation planning.

4.2 A landfill shall not be sited within ecological protection red lines, areas concentrating permanent basic farmland, spring protection zones, areas of intense karst development with numerous sinkholes and karst funnels, or other areas requiring special protection.

4.3 The site elevation shall be above the flood level with a return period of not less than 50 years, and outside the inundation and protection zones of reservoirs and other artificial water storage facilities in long-term plans. For valley landfills with reliable flood defences, where the environmental impact assessment shows the flood risk to be acceptable, this criterion may be relaxed as appropriate.

4.4 The site shall avoid: destructive seismic zones and active tectonic areas; active collapse, landslide and uplift zones; active fault zones; limestone cave development zones; key groundwater pollution control zones; active subsidence areas of abandoned mines; active sand dunes; areas affected by tsunami and storm surge; wetlands; unstabilised alluvial fans and gullies; peat; and other areas that may endanger landfill safety. Where a site in a limestone cave development zone cannot be avoided, a geologically stable site shall be chosen through site investigation and effective engineering measures taken to improve stability.

4.5 The siting relationship and protective distances between the landfill and residences, surface water bodies, motorways, trunk roads, railways, airports, military bases and other sensitive receptors shall be determined by the environmental impact assessment and its approval.

5 Design, construction and acceptance requirements

5.1 General provisions

5.1.1 According to local natural conditions and the characteristics of the waste, the landfill shall be provided with: weighing facilities, a waste dam, a liner system, a leachate collection and drainage system, a leachate treatment system, flood control, separation of rainwater and leachate, groundwater drainage, landfill gas drainage and treatment, cover and closure systems, environmental monitoring facilities, emergency facilities and other utilities.

5.1.2 Rainwater and leachate shall be kept separate. A rainwater collection system shall collect and discharge rainwater from the catchment that could flow towards the landfill area and rainwater in unfilled areas that has not touched waste. This rainwater shall not be mixed with leachate.

5.1.3 The bottom of the foundation layer of the landfill area shall be at least 3 m above the highest annual groundwater level. Where the distance is less than 3 m, a groundwater drainage system designed to GB 50869 shall be built.

5.1.4 The landfill shall be enclosed by walls or fences, with litter screens, safety protection and firebreaks at the boundary of the landfill area and other necessary locations.

5.2 Design of the liner system

5.2.1 A single or double composite liner system shall be selected according to the geology of the natural foundation layer and the conclusions of the environmental impact assessment.

5.2.2 Where the saturated hydraulic conductivity of the natural foundation layer is not more than 1.0 x 10^-5 cm/s and its thickness is not less than 2 m, a single composite liner may be used, provided that: a) the synthetic liner is high density polyethylene (HDPE) geomembrane not less than 2.0 mm thick; b) beneath it lies a natural or modified clay liner not less than 0.75 m thick with a compacted saturated hydraulic conductivity of not more than 1.0 x 10^-7 cm/s.

5.2.3 Where the saturated hydraulic conductivity of the natural foundation layer exceeds 1.0 x 10^-5 cm/s, or its thickness is less than 2 m, a double composite liner shall be used, provided that: a) the synthetic liners are HDPE geomembrane, the primary liner not less than 2.0 mm and the secondary liner not less than 1.5 mm thick; b) beneath them lies a natural or modified clay liner not less than 0.75 m thick with a compacted saturated hydraulic conductivity of not more than 1.0 x 10^-7 cm/s; c) a leak detection layer of fine gravel, geocomposite drainage net or similar material is placed between the two liners to collect, drain and detect liquid passing through the primary liner.

5.2.4 The saturated hydraulic conductivity of clay liners shall be measured by the falling head permeability test of GB/T 50123. HDPE geomembrane shall meet CJ/T 234.

5.2.5 Materials used instead of synthetic or clay liners shall have at least equivalent water-tightness.

5.2.6 Independent landfill cells receiving fly ash from municipal solid waste incineration or residues from medical waste incineration (fly ash and bottom ash) shall meet the double composite liner requirements of 5.2.3.

5.2.7 The landfill shall be able to monitor liner leakage so that leaks are detected in time, by one or more of: liner leak monitoring equipment, groundwater monitoring wells, a leak detection layer.

5.3 Design of leachate collection, drainage and treatment systems

5.3.1 A leachate collection and drainage system shall be provided, designed so that the leachate head on the liner does not exceed 30 cm during operation, closure and post-closure maintenance and management.

5.3.2 A leachate equalization basin shall be provided, lined to a standard not lower than that of the landfill area. Its capacity shall be calculated to GB 50869.

5.3.3 Leachate treatment facilities shall be built according to local conditions and leachate generation, so that leachate is treated to the standard throughout operation, closure and post-closure maintenance and management.

5.3.4 Where leachate treatment facilities are built, the equalization basin shall be enclosed under negative pressure suction, with the extracted gas treated to the standard by chemical absorption, biological or adsorption deodorisation. The enclosure design shall allow for rainwater drainage, gas venting and removal of sludge from the basin floor.

5.4 Design of landfill gas drainage and treatment systems

5.4.1 A landfill gas drainage system shall be provided.

5.4.2 Landfills with a design capacity of not less than 2.5 million tonnes and a waste depth exceeding 20 m shall build landfill gas utilisation or flare facilities, giving priority to efficient utilisation.

5.4.3 Smaller landfills without the conditions for gas utilisation shall use a semi-aerobic landfill process that effectively reduces methane generation and emission, or treat landfill gas by flaring, biocovers or biofilters. Where the semi-aerobic process is used, the leachate drainage pipes shall be connected to the vertical gas vents and open to the atmosphere, and their outlets shall be kept above the leachate level in the equalization basin or collection well.

5.5 Construction and acceptance requirements

5.5.1 The construction plan shall include quality assurance and quality control measures, and define pollution control measures during construction and the responsibilities of the parties.

5.5.2 Clay liners shall be constructed to CJJ 176. HDPE geomembrane laying and welding shall comply with CJJ 113. After construction of the landfill area, the integrity of the HDPE geomembrane shall be tested to CJJ/T 214.

5.5.3 After the synthetic liner is laid, effective engineering measures shall prevent the liner and geotextile in unfilled areas from direct exposure to sunlight.

5.5.4 The environmental protection completion acceptance shall cover liner integrity, the leachate collection and drainage system, the leachate treatment system, the groundwater drainage system and the landfill gas drainage and treatment system, including their commissioning performance.

6 Requirements for wastes accepted for landfill

6.1 The following wastes may be landfilled directly: a) municipal solid waste collected by sanitation agencies or collected by the generator; b) bottom ash from municipal solid waste incineration (excluding fly ash); c) solid residues from composting of municipal solid waste; d) general industrial solid waste similar in nature to municipal solid waste; e) solid waste from other municipal solid waste treatment facilities, other than b) and c); f) solid residues from recycling of renovation and demolition waste.

6.2 Medical waste that meets the disposal exemption provisions of the National Catalogue of Hazardous Wastes may be landfilled after disinfection and shredding.

6.3 Fly ash from municipal solid waste incineration and residues from medical waste incineration (fly ash and bottom ash) may be landfilled only in independent landfill cells, and only where: a) the dioxin content is below 3 micrograms TEQ/kg; b) the concentrations of hazardous constituents in the leachate prepared to HJ/T 300 are below the limits of Table 1.

Table 1 Control limits for pollutants in leachate (mg/L), with test methods: 1 total mercury 0.05 (GB/T 15555.1, HJ 702); 2 total copper 40 (HJ 751, HJ 752, HJ 766, HJ 781); 3 total zinc 100 (HJ 766, HJ 781, HJ 786); 4 total lead 0.25 (HJ 766, HJ 781, HJ 786, HJ 787); 5 total cadmium 0.15 (HJ 766, HJ 781, HJ 786, HJ 787); 6 total beryllium 0.02 (HJ 752, HJ 766, HJ 781); 7 total barium 25 (HJ 766, HJ 767, HJ 781); 8 total nickel 0.5 (GB/T 15555.10, HJ 751, HJ 752, HJ 766, HJ 781); 9 total arsenic 0.3 (GB/T 15555.3, HJ 702, HJ 766); 10 total chromium 4.5 (GB/T 15555.5, HJ 749, HJ 750, HJ 766, HJ 781); 11 hexavalent chromium 1.5 (GB/T 15555.4, GB/T 15555.7, HJ 687); 12 total selenium 0.1 (HJ 702, HJ 766).

6.4 Except for 6.1 d), other general industrial solid waste may be landfilled only in independent landfill cells, after treatment, where the concentrations of hazardous constituents in the leachate prepared to HJ/T 300 are below the limits of Table 1.

6.5 Solid residues from anaerobic digestion and other biological treatment, treated residues of faeces, and sludge from domestic wastewater treatment plants treated to a moisture content below 60% may be landfilled. Sludge for co-landfilling shall also meet GB/T 23485.

6.6 Unless otherwise specified by national ecological and environmental standards, the following shall not be landfilled: a) hazardous waste other than that meeting 6.2, 6.3 and the exemption provisions of the National Catalogue of Hazardous Wastes; b) untreated kitchen waste; c) untreated faeces; d) livestock and poultry farming waste; e) electronic waste and its treatment residues; f) any liquid waste or wastewater other than the leachate generated by the landfill itself.

7 Operation requirements

7.1 Before operation begins, an emergency response plan for environmental incidents shall be prepared, covering leakage from the landfill area and the equalization basin, groundwater pollution and secondary environmental incidents.

7.2 Leachate shall not be spilled during on-site transport of waste, and vehicles shall be washed before leaving the site.

7.3 Landfilling shall proceed by zones and cells. Waste outside the working face shall be covered promptly, and the working face shall be covered at the end of each day.

7.4 Odour shall be reduced by limiting the working face, spraying deodorant, prompt covering and negative pressure extraction under the membrane. In still air and other adverse weather, covering, spraying frequency and extraction shall be increased.

7.5 Leachate recirculation shall not adversely affect landfill stability, and shall stop immediately when poor drainage prevents stability requirements from being met.

7.6 Leachate recirculation shall control odour. Surface spraying and other surface recirculation methods shall not be used. With vertical well or horizontal pipe recirculation, odour escape from the wells or pipes shall be prevented.

7.7 During operation, the effectiveness of the leachate drainage system shall be checked regularly.

7.8 During operation, slope stability shall be checked to CJJ 176. During operation, closure and post-closure management, water levels in the waste body shall be monitored to CJJ 176, and measures taken to lower the leachate level and improve slope stability when the main water level approaches or exceeds the warning level.

7.9 During operation, closure and post-closure management, liner integrity shall be tested every three years, and the environmental risk of the landfill assessed periodically using these results and groundwater quality. Where the risk is high, the emergency measures of 7.10 shall be taken.

7.10 Where signs of groundwater pollution are found, the cause and leak location shall be identified promptly and emergency and pollution control measures started, such as groundwater pump and treat, extraction of leachate from the waste body, liner repair or vertical cut-off barriers.

7.11 Operating records shall be kept throughout operation, closure and post-closure management, including vehicle registrations and numbers, waste quantities, material consumption, landfilling records, leachate and landfill gas collection and treatment, closure and post-closure management, environmental monitoring data, and the source, type, quantity and location of non-municipal solid wastes landfilled.

8 Closure and post-closure maintenance and management requirements

8.1 When landfilling reaches the design level, closure cover and an environmental baseline investigation shall be carried out promptly to GB 51220.

8.2 The closure cover system shall comprise a gas drainage layer, a barrier layer, a drainage layer, a soil cover layer and a vegetation layer.

8.3 The gas drainage layer shall be connected to the vertical gas vents, which shall be installed to CJJ 133.

8.4 The closure cover shall be graded to GB 51220 to keep the waste body stable and prevent rainwater erosion.

8.5 The closure cover shall be combined with ecological restoration, and damage to the barrier and drainage layers by deep-rooted plants shall be prevented.

8.6 The integrity of the cover barrier layer shall be tested after construction.

8.7 After closure, the leachate collection and drainage system shall continue to be operated and maintained, leachate and landfill gas shall continue to be treated and monitored, until pollutant concentrations in the leachate have been below the limits of Tables 2 and 3 for two consecutive years.

8.8 Before landfill land is developed, environmental investigation and risk assessment shall be carried out to HJ 25.1, HJ 25.2 and HJ 25.3. Use of a stabilised site shall also meet the stabilisation criteria of GB/T 25179.

8.9 Complete records of the landfill, covering site selection, survey, land acquisition, design, construction, acceptance, operation, closure and post-closure management, monitoring and emergency response, shall be organised, filed and kept in accordance with national archives laws and regulations.

9 Pollutant discharge control requirements

9.1 Control requirements for direct discharge of water pollutants

9.1.1 Existing and new landfills discharging water pollutants directly shall meet the limits of Table 2.

Table 2 Discharge limits for water pollutants, direct discharge: 1 colour (dilution ratio) 40; 2 chemical oxygen demand (CODCr) 100 mg/L; 3 biochemical oxygen demand (BOD5) 30 mg/L; 4 suspended solids 30 mg/L; 5 total nitrogen 40 mg/L; 6 ammonia nitrogen 25 mg/L; 7 total phosphorus 3 mg/L; 8 faecal coliforms 10 000 per litre; 9 total copper* 0.5 mg/L; 10 total zinc* 1 mg/L; 11 total mercury 0.001 mg/L; 12 total cadmium 0.01 mg/L; 13 total chromium 0.1 mg/L; 14 hexavalent chromium 0.05 mg/L; 15 total arsenic 0.1 mg/L; 16 total lead 0.1 mg/L; 17 total beryllium* 0.002 mg/L; 18 total nickel* 0.05 mg/L.

Items marked * are additional pollutants to be controlled where fly ash from municipal solid waste incineration is landfilled. Monitoring location for all items: discharge outlet of the leachate treatment facility.

9.1.2 In areas where land development density is already high and environmental carrying capacity is weakening, or where environmental capacity is small and the ecological environment fragile, so that serious pollution is likely and special protection is needed, such as key groundwater pollution control zones, landfill discharges shall be strictly controlled and direct discharges shall meet the special limits of Table 3. The geographical scope and timing of the special limits are set by the ecological and environmental department of the State Council or by provincial people's governments.

Table 3 Special discharge limits for water pollutants, direct discharge: 1 colour (dilution ratio) 30; 2 CODCr 60 mg/L; 3 BOD5 20 mg/L; 4 suspended solids 30 mg/L; 5 total nitrogen 20 mg/L; 6 ammonia nitrogen 8 mg/L; 7 total phosphorus 1.5 mg/L; 8 faecal coliforms 1 000 per litre; 9 total copper* 0.5 mg/L; 10 total zinc* 1 mg/L; 11 total mercury 0.001 mg/L; 12 total cadmium 0.01 mg/L; 13 total chromium 0.1 mg/L; 14 hexavalent chromium 0.05 mg/L; 15 total arsenic 0.1 mg/L; 16 total lead 0.1 mg/L; 17 total beryllium* 0.002 mg/L; 18 total nickel* 0.05 mg/L.

Items marked * are additional pollutants to be controlled where fly ash from municipal solid waste incineration is landfilled. Monitoring location for all items: discharge outlet of the leachate treatment facility.

9.2 Control requirements for indirect discharge of water pollutants

9.2.1 A landfill discharging water pollutants to a centralised wastewater treatment facility shall agree with its operator, in a legally binding written contract, the quality and quantity, discharge method, monitoring, information sharing, emergency response, liability for breach and dispute resolution. Centralised facilities include municipal and industrial wastewater treatment plants.

9.2.2 Treated leachate shall be discharged evenly and shall not affect the normal operation and performance of the centralised facility.

9.2.3 Leachate discharged to a centralised facility shall meet the following: a) it shall reach a municipal plant through the main sewer, through a dedicated pipe to the main sewer where direct connection is not possible, or as provided by national regulations where neither is possible; b) it shall reach an industrial plant through a dedicated pipe, or as provided by national regulations where no pipe can be laid; c) water pollutants shall meet the limits of Table 4.

Table 4 Discharge limits for water pollutants, indirect discharge: 1 colour (dilution ratio) 64; 2 CODCr 500 mg/L; 3 BOD5 350 mg/L; 4 suspended solids 400 mg/L; 5 total nitrogen 70 mg/L; 6 ammonia nitrogen 45 mg/L; 7 total phosphorus 8 mg/L; 8 total copper* 2 mg/L; 9 total zinc* 5 mg/L; 10 total mercury 0.001 mg/L; 11 total cadmium 0.01 mg/L; 12 total chromium 0.1 mg/L; 13 hexavalent chromium 0.05 mg/L; 14 total arsenic 0.1 mg/L; 15 total lead 0.1 mg/L; 16 total beryllium* 0.002 mg/L; 17 total nickel* 0.05 mg/L.

Items marked * are additional pollutants to be controlled where fly ash from municipal solid waste incineration is landfilled. Monitoring location for all items: discharge outlet of the leachate treatment facility.

9.3 Methane

The methane content above the landfill shall be less than 5%, and inside landfill buildings and structures less than 1.25%.

9.4 Air pollutants

Emissions of air pollutants, including odour pollutants, shall comply with GB 16297 and GB 14554.

10 Monitoring requirements

10.1 General requirements

10.1.1 The landfill shall establish a self-monitoring system and programme in accordance with the law, the Regulations on the Administration of Pollutant Discharge Permits, the Measures for the Administration of Environmental Monitoring and HJ 819, monitor its discharges and their effect on surrounding environmental quality, keep original records, and publish self-monitoring results on the national pollutant discharge permit information platform.

10.1.2 Installation and maintenance of automatic monitoring equipment shall follow the law, the Measures for the Administration of Automatic Monitoring of Pollution Sources and the discharge permit.

10.1.3 Permanent sampling ports, sampling platforms and outlet signs shall be designed, built and maintained in accordance with environmental monitoring rules and technical specifications.

10.1.4 Monitoring method standards issued after this standard may also be used for the corresponding items where they are suitable.

10.2 Monitoring of water pollutant discharges

10.2.1 Sampling points and sampling methods shall follow HJ 91.1.

10.2.2 The discharge outlet of the leachate treatment facility shall be monitored online. Pollutants without an online monitoring specification shall be monitored manually at least once a month. Monitoring data shall be shared promptly with the ecological and environmental authority and with the operator of the centralised wastewater facility.

10.3 Groundwater monitoring

10.3.1 Groundwater monitoring wells shall meet the siting requirements of HJ 164 and also: a) one background well upstream, at least two pollution surveillance wells downstream, and at least one pollution dispersion well on each side of the landfill; b) where there is a groundwater drainage system, one pollution monitoring well at the drainage pipe outlet; c) wells built and managed to HJ 164; d) additional wells as appropriate for large landfills.

10.3.2 Where aquifers are deep or wells are difficult to place, the number of wells may be set according to hydrogeological conditions and environmental risk.

10.3.3 Background groundwater quality shall be monitored before the landfill is used, and monitoring shall continue from the start of use.

10.3.4 Groundwater parameters: pH, total hardness, total dissolved solids, oxygen consumption (CODCr method), ammonia nitrogen, nitrate, nitrite, sulphate, chloride, volatile phenols, cyanide, arsenic, mercury, total chromium, hexavalent chromium, lead, fluoride, cadmium, iron, manganese, copper, zinc, nickel, beryllium and total coliforms.

10.3.5 During operation, the well at the drainage pipe outlet shall be sampled at least weekly, pollution dispersion and surveillance wells at least every two weeks, and the background well at least monthly. After closure, groundwater monitoring shall continue at least quarterly. Abnormal results shall be re-monitored within 3 days, with additional parameters as necessary.

10.4 Fly ash

Fly ash from municipal solid waste incineration meeting 6.3 shall be monitored to HJ 1134 before landfilling.

10.5 Methane monitoring

10.5.1 Methane sampling points above the landfill and inside buildings and structures shall be placed to GB/T 18772, and monitored at least daily.

10.5.2 Methane in air shall be measured with portable analysers meeting GB 13486 or equivalent. Enforcement monitoring shall use the method of HJ 604.

10.6 Air pollutant monitoring

10.6.1 Monitoring factors for fugitive odour emissions shall match the items controlled by GB 14554. Factors for other fugitive gas emissions shall be chosen to represent the characteristics of the landfilled waste.

10.6.2 Sampling points, sampling and methods shall follow GB 16297 and HJ 905, with the downwind side of the source as the main monitoring area.

10.6.3 During operation, odour pollutants and fugitive gases at the site boundary shall be monitored at least monthly and at least quarterly respectively. Abnormal results shall be re-monitored within one week.

10.6.4 Landfills with leachate treatment facilities shall monitor ducted odour emissions for the items controlled by GB 14554 at least quarterly, re-monitoring abnormal results within one week.

10.7 Methods for determining pollutant concentrations

Pollutant concentrations shall be determined by the method standards listed in Table 5.

Table 5 Method standards for pollutant concentrations: 1 colour HJ 1182; 2 CODCr HJ/T 70, HJ/T 132, HJ/T 399, HJ 828; 3 BOD5 HJ 505; 4 suspended solids GB 11901; 5 ammonia nitrogen HJ 195, HJ 535, HJ 536, HJ 537, HJ 665, HJ 666; 6 total nitrogen HJ 636, HJ 667, HJ 668, HJ 199; 7 total phosphorus GB 11893, HJ 670, HJ 671; 8 total mercury GB 7469, HJ/T 341, HJ 597, HJ 694; 9 total arsenic GB 7485, HJ 694, HJ 700, HJ 776; 10 total cadmium GB 7471, GB 7475, HJ 700, HJ 776; 11 total chromium GB 7466, HJ 700, HJ 757, HJ 776; 12 hexavalent chromium GB 7467, HJ 908; 13 total lead GB 7470, GB 7475, HJ 700, HJ 776; 14 total copper GB 7475, HJ 485, HJ 486, HJ 700, HJ 776; 15 total zinc GB 7472, GB 7475, HJ 700, HJ 776; 16 total beryllium HJ/T 59, HJ 700, HJ 776; 17 total nickel HJ 700, HJ 776; 18 faecal coliforms HJ 347.1, HJ 347.2, HJ 1001; 19 methane HJ 604.

11 Implementation and supervision

11.1 Implementation of this standard is supervised by the ecological and environmental authorities.

11.2 Under all circumstances the landfill shall comply with the pollutant discharge control requirements of this standard and keep its pollution control facilities in normal operation. In enforcement monitoring, ecological and environmental authorities at all levels may take samples on site and use the results to decide whether discharges comply with the standard and to apply environmental management measures, and may use automatic monitoring systems to collect evidence of violations.

......
This preview omits tables, figures, formulas and parts of the technical clauses. The complete document — 17 pages — is available in the English PDF.

Referenced standards

Normative references

GB 7466 · GB 7467 · GB 7469 · GB 7470 · GB 7471 · GB 7472 · GB 7475 · GB 7485 · GB 11893 · GB 11901 · GB/T 50123 · HJ/T 59 · CJJ 133

Cited by

Similar standards

Editions of GB 16889

EditionTitleRevisionStatus
GB 16889-2024Standard for pollution control on the landfill site of municipal solid wastecurrent editionCurrent
GB 16889-2008Standard for pollution control on the landfill site of municipal solid wasteprevious editionSuperseded

This page sells the current edition, GB 16889-2024. Earlier editions are listed for reference only.

How to Download GB 16889-2024

  1. 1

    Add to cart

    Click "Download PDF" on this page and choose "Buy this standard". You can add more standards before checkout.

  2. 2

    Checkout

    Enter your email and billing details. Payment is processed securely by Stripe (cards or bank transfer). Prefer bank details? Request a quotation (min. order $300).

  3. 3

    Instant delivery (0–9 sec)

    Delivery is automatic: within seconds of payment you'll receive an email with a secure download link. The link stays valid for 72 hours.

  4. 4

    Invoice included

    A tax invoice is attached to the confirmation email. Need a custom invoice? Contact us.

Related Standards

English PDF
17 pages
Instant delivery (0–9 sec)
Invoice included
View Cart

Secure payment via Stripe

Payments accepted

VisaMastercardAmerican ExpressApple PayGoogle PayStripe

GB 16889-2024

$240.00