GB 14287.4-2014Electrical fire monitoring system - Part 4: Arcing fault detectors (English PDF)
电气火灾监控系统 第4部分:故障电弧探测器
Open the GB 14287.4-2014 preview as PDF
This is a limited preview
Buy now to download the full PDF (24 pages)
Issued by
AQSIQ; SAC
Level / Type
National · Mandatory
Issue date
June 24, 2014
Implementation date
June 1, 2015
Scope
GB 14287.4-2014 is the English-translated version of 电气火灾监控系统 第4部分:故障电弧探测器.
Part 4 of GB 14287 covers the arcing fault detector, the hardest of the family to build: the device that recognises the current signature of a series or parallel arc - a broken conductor, a loose terminal, a damaged insulation - and distinguishes it from the arcing that normal loads such as motors, dimmers and switching supplies produce all the time. The standard sets the requirements for detection and for non-operation on those normal loads, the test methods with the arc generator, the inspection rules, the marking and the operating instructions, with an informative annex showing typical fault waveforms. Issued on 24 June 2014, in force since 1 June 2015; it is the first edition of this part. This page is published from the official record of the standard held by the Chinese standards administration: the identification, the dates, the classification and the edition it replaces are taken from there. The clause text, the tables and the numeric limits are not reproduced on this page - they are in the document itself, which is delivered in full in English translation.
Document preview — GB 14287.4-2014
National Standard of the People's Republic of China
- ICS
- 13.220.20
- Classification
- C 81
Issued by: General Administration of Quality Supervision, Inspection and Quarantine; Standardization Administration of the PRC
Contents
- 1 Scope
- 2 Normative references
- 3 Terms and Definitions
- 4 Microwave 1100W high fire up and running 10
- 5 Requirements
- 5.3 Basic requirements
- 5.4 Alarm Properties
- 5.8 Use AC220V/50Hz AC power supply of the detector at
- 5.11 Mechanical environmental resistance
- 5.12 The main component performance
- 5.12.2 Indicators
- 5.12.6 Terminal
- 6 Test
- 6.1 General
- 6.1.4 Visual inspection 1 1-4 2
- 6.2 Basic requirements for inspection
- 6.3 Performance Test 1-4 1 4
- 6.3.1 Sample connection
- 6.3.2 Arc fault test
- 6.3.3 Test False Alarm
- 6.4 Repeatability test
- 6.4.3 The sample uninterruptible power-1d, and then measuring the required
- 6.5 Voltage fluctuation test 6
- 6.6 Insulation resistance test
- 6.7 Leakage current test 1 8
- 6.8 Electric strength test
- 6.9 Cryogenic 9 (running) Test 1 10
- 6.10 Damp heat (run) Test 2 11
- 6.11 Impact test 2 6.12 3
- 6.14 RFEMS Test 2 15
- 6.15 RF field immunity test conducted disturbances induced by
- 7 Load Suppression Test 2
- 8 Contact discharge (shell conductor and the sample Coupling plate)
- 10 Acceleration m/s
- 12 Crash Test 13
- 20 No power
Foreword
GB this Part 5,7,
8 Chapter 14287 are mandatory, the rest are recommended. GB 14287 "electrical fire monitoring system" consists of the following components.
--- Part 1. Electrical fire monitoring equipment;
--- Part 2. residual current electric fire detectors;
--- Part 3. temperature electrical fire detectors;
--- Part 4. arc fault detector; This section GB of Section 414 287. This section drafted in accordance with GB/T 1.1-2009 given rules. This section presents the People's Republic of China Ministry of Public Security. This part of the National Standardization Technical Committee on Fire fire detection and alarm Technical Committee (SAC/TC113/SC6) centralized. This in part by the Ministry of Public Security is responsible for drafting the Shenyang Fire Research Institute, Ningbo Xi Yu Electronic Development Co., Ltd., Shanghai Hua Su Electrical Technology Co., Secretary, Shenyang Swan Electric Co., Ltd., Fujian Junhao Electronics Co., Ltd. participated in the drafting. The main drafters of this section. Ding Hongjun, Gao Wei, Zhang Ying Cong, Li Xiaobai, Cao, Liu Changan, Qi Zi Bo, Hu Shaoying, Huang Wujie. Electrical fire monitoring system Part 4. arc fault detector
0.7
Note. The power tolerance of ± 10%. 6.3.2.1.2 After the start of test equipment, if generated per second and up to nine of the following half-cycle arc fault lines or 14 and more than half Arc fault cycle, then this test is an effective test group, observe and record the state of the detector, and alarm recording time sample; if each test Number of seconds of arc generated when the condition is not satisfied, then the test is invalid in this group test should be repeated.
Note. The arc duration not exceeding 0.42ms or current value does not exceed 5% of the rated current value is not as small arc arc statistics.
6.3.2.2 Test equipment and methods 6.3.2.2.1 Test series carbonized arc path 2, the two single-core copper conductor (2.5mm2) after the end of the hinge 2cm insulation removed, the wire insulation to retain overlapping portions 2mm ~ 4mm, with plastic insulation tape around the hinge portion 3 weeks to prepare a sample, the sample test access lines generated by the high-pressure device Set generates a high voltage insulation breakdown so that the overlapped portion is formed carbonized path, from the low voltage (AC220V) device on the line and load, thereby producing Arcing. Figure 2 tandem arc path carbonation test circuit schematic 6.3.2.2.2 carbonation path parallel arc tests 3, the two parallel single-core copper wire (2.5mm2) at an intermediate portion spaced 3mm incision after insulation with plastic insulating tape FIG. Wound incision site three weeks to prepare a sample, the sample test access lines, high voltage generated by the high voltage generator means causes insulation breakdown shaped cutout portion A carbonized path, by a low voltage (AC220V) device on the line and load power supply, resulting in an arc. Figure 3 parallel test circuit schematic carbonized arc path 6.3.2.2.3 parallel metallic contact arc tests As shown, at an angle to the horizontal blade 4 slow down in two parallel multi-core copper wire and placed in parallel (2.5mm2) wire core moment of contact arcing.
4 parallel metallic contact arcing test circuit schematic
1 Scope
Part 4 of GB 14287 covers the arcing fault detector, the hardest of the family to build: the device that recognises the current signature of a series or parallel arc - a broken conductor, a loose terminal, a damaged insulation - and distinguishes it from the arcing that normal loads such as motors, dimmers and switching supplies produce all the time. The standard sets the requirements for detection and for non-operation on those normal loads, the test methods with the arc generator, the inspection rules, the marking and the operating instructions, with an informative annex showing typical fault waveforms. Issued on 24 June 2014, in force since 1 June 2015; it is the first edition of this part. This page is published from the official record of the standard held by the Chinese standards administration: the identification, the dates, the classification and the edition it replaces are taken from there. The clause text, the tables and the numeric limits are not reproduced on this page - they are in the document itself, which is delivered in full in English translation.
GB This section 14287 specifies the terms and definitions arc fault detector, classification, requirements, testing, inspection rules, signs and use Instructions. This section applies install arc fault detector used in industrial and civil buildings 10kW and below electrical circuits. other Apparatus for use in arc fault detector for an electrical fire monitoring, as well as under other environmental arc fault detector with special requirements, Except as otherwise provided by the special requirements of the relevant standards, are also applicable to this section.
2 Normative references
The following documents for the application of this document is essential. For dated references, only the dated version suitable for use herein Member. For undated references, the latest edition (including any amendments) applies to this document. Part 1
GB 4706.1 Safety of household and similar electrical appliances. General requirements
GB/T 9969 General Instructions industrial products
GB 12978 fire electronic products inspection rules
GB 16838 fire electronic products environment test methods and severities
GB/T 17626.2 Electromagnetic compatibility Testing and measurement techniques - Electrostatic discharge immunity test
GB/T 17626.3 electromagnetic compatibility test and measurement technology RFEMS test
GB/T 17626.4 Electromagnetic compatibility Testing and measurement techniques - Electrical fast transient burst immunity test
GB/T 17626.5 electromagnetic compatibility test and measurement technology surge (impact) immunity test
GB/T 17626.6 Electromagnetic compatibility Testing and measurement techniques Immunity to conducted disturbances induced field
GB 23757-2009 fire protection requirements for electronic products
3 Terms and Definitions
The following terms and definitions apply to this document.
3.1 Arc fault arcingfault Since the electrical lines or equipment old and damaged insulation, loose electrical connections, air humidity, voltage and current causes such a sharp increase in air Gas breakdown caused by free gas discharge phenomenon.
3.2 Arc fault detector arcingfaultdetector For detecting protected from electrical lines arc fault detector. Category
4 Arc fault detector (hereinafter referred to as the detector) according to work can be divided into.
a) non-independent;
4 Microwave 1100W high fire up and running 10
5 Iron 1100W By adjusting the temperature control knob, Make contacts and breaking temperature 10 times Electronic variable speed hand drill 800W
6 So that the hand drill from the lowest speed in no-load condition To the highest, from highest to lowest and then 2 times reciprocally 7 with electronic ballasts for fluorescent lamps 36W25 cold state up and running 10 8
3 Cooling mode inverter air conditioner up and running 60 9 infrared disinfection cabinet 700W up and running
10 Composite load (including fixed-frequency electric ice Box with inductive ballast Fluorescent lights, computers, fixed-frequency air) Respectively, 120W, 60W2 lamp, 300W, Air conditioning and heating the way Each interval 5s activate a random electrical equipment 60 11 other necessary test equipment cf. numbers 1 to 10
Note 1. 1 = 2324W.
Note 2. The power tolerance of ± 10%.
6.3.3.2 test equipment as shown in Figure 5 is connected in parallel anti-disturbance test, which is the power load 1000W resistive load. When the test Arc fault generated by adjusting the arc generator (11), when the generating lines up to 14 cycles per second and more than half of the failures Arc, this group test as a valid test, observe and record the state of the detector; if the number of arc per second produced by the test condition is not satisfied When this group test invalid test should be repeated. Figure
5 Requirements
5.1 General Chapter 6 of the detector should be tested, test results should meet the corresponding requirements of Chapter 5.
5.2 appearance requirements No corrosion detector surface, coating loss and blistering, no scratches, cracks, burrs and other mechanical damage, no loose fastening parts.
5.3 Basic requirements
5.3.1 use AC220V/50Hz AC power supply detector, power line input terminals should be located.
5.3.2 The detector should have a red light alarm acknowledgment. When a monitored area parameters meet the alarm condition, the detector alarm confirmation light should point Bright and kept to be reset. Confirm its lamp is lit in front of 3m at no more than 500lx illuminance environmental conditions, should be clearly visible.
5.3.3 Detector When connecting other auxiliary devices (such as remote confirmation lights, control relays, etc.), and the auxiliary device is connected between the line and disconnection Short circuit should not affect the normal operation of the detector.
5.3.4 Detector factory settings should not be easily changed. When the need to change the need to use special means (such as special tools or password), No It should not destroy its seals.
5.3.5 If the performance of the detector alarm can be set the scene on the detector or monitoring device connected thereto, shall meet the following Claim.
a) When the manufacturer declares that all settings meet the requirements of this section, any probe under the conditions set by this section shall meet Requirements, and for the field should be set only by special tools, password, or separate probe and the base means to achieve;
b) When the manufacturer declares that a setting does not satisfy the requirements of this section, which should be set only by special tools, means of achieving password, And this should be clearly indicated on the detector provided relevant documents or can not meet the requirements of this section.
5.3.6 protective properties of the detector should meet the requirements of GB 23757-2009 in 3.2.1.
5.4 Alarm Properties
5.4.1 When the 14 and more than half an arc fault is detected the line cycle occurs within 1s, the detector should send an alarm signal in the 30s Number, alarm LED lights; non-independent detector alarm indication should be kept to the connected electrical fire monitoring device reset, freestanding Detector alarm indication should be kept to a manual reset.
5.4.2 When the probe line and arc fault occurred nine the following half-cycle is within 1s, the detector should be visual and audible alarm signal And control signals, but it may take other forms of prompts.
5.4.3 The detector shall be provided with a set of control output when an alarm signal, the control output should be in operation within 1s.
5.4.4 false alarm detector test, alarm and control signals should not be issued.
5.4.5 detector inhibition test process loads should alarm and control signals in the 30s.
5.5 Repeatability Repeat 3 times measuring detector alarm time, power 1d and then measured three times the alarm time, the alarm time should meet the requirements of 5.4. During energized, the detector should alarm and fault signals.
5.6 voltage fluctuation performance Use AC220V/50Hz AC power supply of the detectors in the power supply voltage of AC187V and AC242V conditions, should To work properly, the alarm time should meet the requirements of 5.4.
5.7 Insulation resistance Insulation resistance detector external charging terminals and the chassis between not less than 20MOmega; 220V/50Hz AC power input and Insulation resistance value between the cabinet should not be less than 50MOmega. Leakage current
5.8 Use AC220V/50Hz AC power supply of the detector at
1.06 times the rated voltage, the leakage current value should not exceed 0.5mA.
5.9 Electric strength Between use AC220V/50Hz AC power supply probe power plug (or power terminals) and the chassis should be able to withstand frequent Rate of 50Hz, valid values AC1250V voltage test lasted 1min the electric strength. During the test, the detector should strike occurs Wear phenomenon; After the test, the detector performance shall comply with the requirements of 5.4.
5.10 Climate tolerance The detector should be able to withstand the test specified in Table 1 under the climate conditions. During the test, the detector should be kept normal surveillance state; After the test, it should be no damage to the coating and corrosion detector alarm time should meet the requirements of 5.4. Climate conditions in Table 1 running test requirements Name of Test Test Parameters Test Conditions Operating status Low temperature (running) test temperature -10 ± 3 duration Normal monitoring state Damp (run) test temperature 40 ±
5.11 Mechanical environmental resistance
5.11.1 Test run Detectors should be able to withstand the test at the table under the second mechanical environmental conditions. During the test, it should maintain a normal monitoring state; test After, there should be no mechanical damage and tighten loose parts, the detector alarm time should meet the requirements of 5.4. Table
2 Run test mechanical environmental conditions Name of Test Test Parameters Test Conditions Operating status Impact test Peak acceleration m/s
2 Adhesive red time ms Impact direction 100-20m (quality m<=4.75kg time) 0 (mass m > 4.75kg time) Normal monitoring state Crash Test Hammerhead speed m/s 1.5 ±
0.125 Collision kinetic energy 1.9 ±
0.1 The number of collisions
5.12 The main component performance
5.12.1 General requirements The main components of the detector should comply with relevant standards of styling products.
5.12.2 Indicators
5.12.2.1 Each application Chinese lights are clearly marked its features.
5.12.2.2 Indicator apply color logo, red indicates an alarm condition; yellow indicates a fault condition; Green indicates normal state.
5.12.2.3 lights in front of it at 3m, at no more than 500lx illuminance environmental conditions, should be clearly visible.
5.12.3 Display In no more than 500lx illuminance environmental conditions, the information should be displayed at the front of 0.8m, clearly readable 22.5 ° viewing angle range.
5.12.4 Sound Devices Under normal operating conditions, away from the front of the detector at 1m SPL (A-weighted) of not less than 70dB.
5.12.5 switches and buttons (button) Switches and buttons (button) operation should be flexible, reliable, feature clearly labeled.
5.12.6 Terminal
5.12.6.1 detector should be located terminals connected to the external lines.
5.12.6.2 terminals should be clearly marked its features.
5.12.6.3 strong power terminals should be located inside the detector or safe, reliable protection measures to protect.
5.12.6.4 electric and electronic terminals shall be provided separately.
6.1 General
6.1.1 Test atmospheric conditions Except as otherwise stated in the relevant provisions, the various tests are carried out under the following atmospheric conditions.
--- Temperature. 15 °C ~ 35 °C;
--- Humidity. 25% to 75%;
--- Atmospheric pressure. 86kPa ~ 106kPa.
6.1.2 Test normal monitoring state When no special requirements in the relevant provisions, should ensure that the detector's operating voltage is rated voltage, and to remain active during the test Voltage stability.
6.1.3 Tolerance In addition to the relevant provisions otherwise indicated, are the tolerance test data ± 5%; ambient condition parameters deviation should be consistent with GB 16838 Claim.
6.1.4 Visual inspection Test sample (hereinafter referred to as the sample) before testing should be visually examined after the test can be carried out in line with the requirements of 5.2.
6.1.5 Sample 4 sets of detectors, and be numbered before the test.
6.1.6 Detector Installation Normal installation specimen shall be specified by the manufacturer to install. If the specification is given a variety of installation, the test should be used in the sample Installation work most unfavorable way.
6.1.7 Test Procedure According to the procedure specified in Table 5 were tested. Table 5 test procedure Sample No. No. No. Terms of pilot projects
6.2 Basic requirements for inspection
6.2.1 For use AC220V/50Hz AC power supply of samples, checking samples of the power input terminals.
6.2.2 The sample alarm, alarm checking samples to confirm lamp; manual reset sample, observe and record the working status of the sample.
6.2.3 Sample connection for auxiliary equipment, respectively, the auxiliary device connection line open and short circuits, observe and record the working status of the sample.
6.2.4 factory inspection sample setting status.
6.2.5 For a sample site alarm parameters can be set, check the setting status of the sample.
6.2.6 in accordance with the requirements of
4.2 in GB 23757-2009 carried enclosure class test.
6.3.1 Sample connection
6.3.1.1 Performance test specimens shall be the actual alarm circuit or equivalent arc fault simulation generating means. The actual test circuit Test the connection diagram shown in Figure 1a), the arc fault simulation generator diagram shown in Figure 1b), the typical arc fault waveform see Figure Appendix A. Test connection
a) actual circuit
b) analog generating means
1 arc fault test circuit schematic diagram
6.3.1.2 arc fault simulation generating means technical indicators should meet the following requirements.
a) a voltage output terminal. output voltage value AC220 × (1 ± 10%) V; current output <=2A; signal bandwidth is not less than 20kHz.
b) current output terminal. output voltage is AC20V ~ 60V; current output <=60A.
c) the maximum single working time. 5min.
d) Power supply. AC220V.
6.3.2 Arc fault test
6.3.2.1 Test procedure 6.3.2.1.1 The arc load conditions and the nature of the desired Table 6, the samples were tested. Table 6 arc fault test Arc arc path parallel nature series carbonized carbonized path parallel arc metal arc contact Load conditions power kV · A
6.3.3 Test False Alarm
6.3.3.1 The samples were as shown in Table 7 false alarm test equipment. Table
7 Test False Alarm No. Name Test Method for power operation mode Test time Under capacitor start motor 2200W load situation random start and stop 2 times 10 2 vacuum cleaner 1200W When turned on, so that by adjusting the speed control knob Vacuum cleaner from lowest to highest speed, then From highest to lowest reciprocate 5 times 3 cooker 2000W 1800W start at 10 and running gear
6.4 Repeatability test
6.4.1 Connect the sample and supporting monitoring equipment. 6.3,
6.4.2 provisions measured three times the alarm time, two measurements of time intervals of not less than 10min, but not more than 1h. last one After the measurement, the sample kept unchanged.
6.4.3 The sample uninterruptible power-1d, and then measuring the required
6.3 times the alarm time, two measurements of time intervals of not less than 10min, but not more than 1h.
6.5 voltage fluctuation test
6.5.1 The samples are arranged according to the normal job requirements. Adjustment test equipment, test equipment so that the output voltage is AC187V/50Hz, The output voltage is applied to the power input of the sample, power, observe the status of the sample. The method according to the provisions of
6.3 alarm performance Test, and alarm recording time sample.
6.5.2 The samples are arranged according to the normal job requirements. Adjustment test equipment, test equipment so that the output voltage is AC242V/50Hz, The output voltage is applied to the power input of the sample, power, observe the status of the sample. The method according to the provisions of
6.3 alarm performance Test, and alarm recording time sample.
6.6 Insulation resistance test
6.6.1 Test procedure By means of insulation resistance test were applied to 500V ± 50V DC voltage to the following section of the sample, continued 60s ± 5s, measuring The insulation resistance v...
7 Load Suppression Test 2
8 Load Suppression Test 3 6.3.4.1.2 suppression capacitor filter The circuit of Figure 9 connecting test equipment, shielding the figure load is 1000W resistive load. 6.3.4.1.1 The method according to the occurrence of electrical Arc and test samples. FIG. 9 capacitor filter suppression test 6.3.4.1.3 line impedance suppression 10 a circuit diagram showing the test equipment is connected, the load is 1000W FIG resistive load. Arcing method in accordance with 6.3.4.1.1 And test samples. twenty one 10 line impedance inhibition test
6.3.4.2 Test Equipment An arc generating means 11, the carbon electrode of 6.4mm and a copper movable electrode includes a stationary diameter. test First move the copper electrode and carbon electrode so that good contact test, the circuit will turn on, start the load device, and then slowly adjust laterally movable electrode It with carbon sequestration, until arcing. 11 arc generating means
12 Crash Test 13
6.13 vibration (sinusoidal) (endurance) test 4 14
20 No power
5.11.3 EMC The detector should be able to withstand the electromagnetic compatibility tests in Table 4 requirements. During the test, it should maintain a normal monitoring state; After the test, the detector Should be able to work properly, the alarm time should meet the requirements of 5.4. Table
4 Electromagnetic compatibility test conditions require Name of Test Test Parameters Test Conditions Operating status RFEMS test Field strength V/m Frequency Range MHz 1 to 1000 Scan rate 10 octave/s <=1.5 × 10-
3 Modulation amplitude 80% (1kHz, sine) Normal monitoring state RF conducted disturbances, induced field Immunity Test Frequency Range MHz
0.15 to 100 Voltage dBµV Modulation amplitude 80% (1kHz, sine) Normal monitoring state Electrostatic discharge immunity test Discharge voltage kV Discharge polarity Discharge interval The number of discharges per point Air discharge (insulator shell Sample)
......
This preview omits tables, figures, formulas and parts of the technical clauses. The complete document — 24 pages — is available in the English PDF.
Referenced standards
Normative references
- GB/T 9969General principles for preparation of instructions for use of industrial products
- GB 12978Rules for test of fire electronic products
- GB 23757-2009Protection requirements for fire electronic products
GB 4706.1 · GB 16838 · GB/T 17626.2 · GB/T 17626.3 · GB/T 17626.4 · GB/T 17626.5 · GB/T 17626.6
Editions of GB 14287.4
| Edition | Title | Revision | Status |
|---|---|---|---|
| GB 14287.4-2014 | Electrical fire monitoring system - Part 4: Arcing fault detectors | current edition | Current |
This page sells the current edition, GB 14287.4-2014. Earlier editions are listed for reference only.
How to Buy GB 14287.4-2014
- 1Add to cart. Click the "Buy GB 14287.4-2014" button on this page. You can add more standards before checkout.
- 2Checkout. Enter your email and billing details. Payment is processed securely by Stripe (cards, Apple Pay, Google Pay supported).
- 3Instant delivery (0–9 sec). Delivery is automatic: within seconds of payment you'll receive an email with a secure download link. The link stays valid for 72 hours.
- 4Invoice included. A tax invoice is attached to the confirmation email. Need a custom invoice? Contact us.
Related Standards
GB 12978-2003 — Rules for test of fire electronic products
GB 12978-2025 — Rules for test of fire electronic products
GB 23757-2009 — Protection requirements for fire electronic products
Secure payment via Stripe
Payments accepted
GB 14287.4-2014