Scope

GB/T 41344.4-2022 is the English-translated version of 机械安全 风险预警 第4部分:措施.

GB/T 41344.4-2022 is the part of the Chinese standard on risk early warning in machinery safety that covers the measures taken. It sets the process of the measures, the input of the warning level, the measures themselves, the escalation of a warning, the evaluation of the measures taken and the cancellation of the warning.

It applies to the risk reduction and protective measures of a risk early warning concerning the safety of machinery. Plant operators, maintenance departments and safety engineers use it. Issued on 9 March 2022, it has applied since 1 October 2022.

Found what you need?

Document preview — GB/T 41344.4-2022

National Standard of the People's Republic of China

ICS
13.110
Classification
J 09

Issued by: State Administration for Market Regulation; Standardization Administration of the PRC

Contents

  • Foreword3
  • Introduction5
  • 1 Scope7
  • 2 Normative references7
  • 3 Terms and Definitions7
  • 4 Process of early-warning measures8
  • 5 Input of the early-warning level9
  • 6 Early-warning measures9
  • 6.1 Types of measures9
  • 6.2 Levels of the measures11
  • 7 Upgrade of the early-warnings12
  • 8 Evaluation of the measures12
  • 9 Cancellation of the early-warnings12
  • Appendix A (Informative) Application example of the early-warning measures13
  • References19

1 Scope

This document specifies the process of early-warning measures, the input of early- warning levels, the early-warning measures, the upgrade of the early-warning, the evaluation of measures, and the cancellation of early-warnings.

This document applies to risk reduction measures or protective measures in risk early- warning related to the safety of machinery.

2 Normative references

The following documents are essential to the application of this document. For the dated documents, only the versions with the dates indicated are applicable to this document; for the undated documents, only the latest version (including all the amendments) is applicable to this standard.

GB/T 30174-2013 Safety of machinery -- Terms

GB/T 41344.1-2022 Safety of machinery -- Risk early-warning -- Part 1: General requirements

GB/T 41344.3-2022 Safety of machinery -- Risk early-warning -- Part 3: Classification

3 Terms and Definitions

The terms and definitions defined in GB/T 30174-2013, GB/T 41344.1-2022 and the followings apply to this document.

3.1 Light signal

Visual identification signs of different levels of risk represented by lights of specific colors.

3.2 Acoustical signal

An auditory alarm emitted by the risk early-warning system according to the level after The types of early-warning measures mainly include information measures, manual measures, and mechanical measures. Select one or more types as required to achieve the purpose of hazard elimination or risk reduction.

Note: See Appendix A for examples of the application of early-warning measures.

6.1.2 Information measures

Information measures mainly include visual signals, auditory signals, text files, etc.

a) Visual signals shall be selected according to different risk levels, and shall have a great degree of discrimination; at the same time, it is necessary to consider the definition of the display of the signal in the environment. Visual signals include but are not limited to:

1) Light signals: lights or combinations of different colors, for example, blue->yellow->orange->red;

2) Screen display: display warning graphics on the screen;

3) Warning signs: highlight the warning signs set in place.

b) Auditory signal: Select the corresponding acoustical signal according to different risk levels, and the signal shall have a high degree of identification; at the same time, it is necessary to consider some influencing factors, such as the acoustical signal's capability of passing through obstacles, the duration, and hearing threshold of human. The influencing factors include at least, but are not limited to:

1) Sound of the alarm;

2) Voice warning.

c) The text file is used to release the early-warning information; the content of the file includes the early-warning time, the information on which the early-warning is classified, the method of early-warning classification, the result of early- warning classification, etc. The documents shall be archived, and the enterprise can determine the retention period and the scope of use of the documents according to its own conditions for subsequent use.

6.1.3 Manual measures
6.1.3.1 Immediate measures

Immediate measures shall be taken for manual intervention when the following situations occur:

--- When the risk is low, but the manual operation is necessary;

--- When the early-warning hasn't been responded to and the risk upgrades;

--- When automatic measures are insufficient to prevent the dangers. Manual intervention measures include, but are not limited to:

--- Manually issue the warnings, etc.;

--- Manually and forcibly control the machines and equipment to perform an emergency stop, power-off, and other operations.

6.1.3.2 Non-immediate measures

Non-immediate measures mainly include behavior management measures, equipment management measures, etc.

a) Behavior management measures include, but are not limited to:

1) Safety education: enable personnel to consciously wear protective equipment as required and operate according to operating procedures;

2) Skill training;

3) Establish a sound safety management system.

b) Equipment management measures include, but are not limited to:

1) Set up warning signs on residual risk equipment;

2) Give information about the use of equipment;

3) Inspect and maintain the equipment regularly.

6.1.4 Mechanical measures

Mechanical measures mainly refer to the measures taken by the machine itself, such as deceleration and shutdown of the robots, the operation of avoiding obstacles by the automatic guided vehicles (AGVs) automatically after encountering people.

6.2 Levels of the measures

According to the early-warning levels classified in GB/T 41344.3-2022, the early- warning measures shall be divided into four levels: level-IV measures, level-III measures, level-II measures, and level-I measures; see Table 1 for details. robot fixture will cause the workpiece to fly out and hurt people; the strength of the holding force can be judged by monitoring the air supply pressure;

d) Workplace's ambient temperature (theta) and humidity (H): Abnormalities of theta and H will accelerate the wear of robot parts and cause the occurrence of the malfunction of the robot; the ambient temperature and humidity of the workplace can be monitored through the temperature and humidity sensor.

A.4 Determination of models and weights

Select the risk value calculation model of formula (1) of GB/T 41344.3-2022. By analyzing historical data and using the expert consultation weight method, determine the weight of each element as shown in Table A.2. Among them, if the limiting cases are monitored, such as the distance between the person and the machine is 0 mm< L< 1000 mm, the vibration acceleration value of the robot fastening screw is a>=10x10-3 m/s2, the air supply pressure of the fixture is 0 kPa< P<=470 kPa or 530 kPa<=P< 1000 kPa, the temperature is theta< 5 °C or theta>45 °C, and the relative humidity is 95%<=H< 100%, then the risk value RvN=1; at this time, the early-warning level is level- I.

The calculation of the risk value (Rvi) of the single factor according to formula (A.1): Where: M1 --- Element of the index; M2 --- Early-warning index; M3 --- Risk value of the factor;

M4 --- Monitored value; if an element is monitored, then M4=1; if it is not monitored, Except for the limiting case where the risk value is RvN=1, the real-time risk value (Rvi) can be calculated by applying formula (1), formula (A.1), and Table A.2 of GB/T 41344.3-2022; see formula (A.2).

When alpha1, beta1, beta2, gamma1, gamma2 is taken as the maximum value respectively, the maximum risk value is Rvmax=0.75.

When alpha1, beta1, beta2, gamma1, gamma2 is taken as the minimum value respectively, the minimum risk

......
This preview omits tables, figures, formulas and parts of the technical clauses. The complete document — 19 pages — is available in the English PDF.

Referenced standards

Similar standards

How to Download GB/T 41344.4-2022

  1. 1

    Add to cart

    Click "Download PDF" on this page and choose "Buy this standard". You can add more standards before checkout.

  2. 2

    Checkout

    Enter your email and billing details. Payment is processed securely by Stripe (cards or bank transfer). Prefer bank details? Request a quotation (min. order $300).

  3. 3

    Instant delivery (0–9 sec)

    Delivery is automatic: within seconds of payment you'll receive an email with a secure download link. The link stays valid for 72 hours.

  4. 4

    Invoice included

    A tax invoice is attached to the confirmation email. Need a custom invoice? Contact us.

Related Standards

English PDF
19 pages
Instant delivery (0–9 sec)
Invoice included
View Cart

Secure payment via Stripe

Payments accepted

VisaMastercardAmerican ExpressApple PayGoogle PayStripe

GB/T 41344.4-2022

$210.00