Scope
GB/T 36995-2018 is the English-translated version of 风力发电机组 故障电压穿越能力测试规程.
GB/T 36995-2018 sets out how to test whether a grid-connected wind turbine can ride through a voltage fault, that is, stay connected and keep running when a grid fault or disturbance makes the voltage drop or rise.
It defines low and high voltage ride-through capability, the fault voltage generating device, the test point, the active power recovery time and the voltage dip, and lists the symbols used.
It then covers the technical requirements for fault voltage ride-through, the test conditions, the test content, the test requirements, the test procedure and what the test report must contain.
Informative annexes deal with successive voltage faults, the measurement of active power, reactive power and voltage, a sample report format and the calculation of reactive current injection. It was issued on 28 December 2018 and has applied since 1 July 2019.
Found what you need?
Document preview — GB/T 36995-2018
National Standard of the People's Republic of China
- ICS
- 27.180
- Classification
- F 11
Issued by: State Administration for Market Regulation; Standardization Administration of the PRC
Contents
- Foreword
- 1 Scope
- 2 Normative references
- 3 Terms and Definitions
- 4 symbol
- 5 fault voltage ride through technical requirements
- 6 Test conditions
- 7 Test content
- 8 test requirements
- 9 test procedure
- 10 Test report content
- Appendix A (informative) Voltage chain fault crossing test requirements and test content
- Appendix B (informative) Active power, reactive power and voltage measurement
- Appendix C (informative) Sample format report
- Appendix D (informative) Determination and calculation method of reactive current injection
- Reference
Foreword
This standard was drafted in accordance with the rules given in GB/T 1.1-2009.
1 Scope
This standard specifies the technical requirements, test conditions, and test conditions for the fault voltage ride-through capability of wind turbines (hereinafter referred to as wind turbines). Content, test requirements, test procedures and test report content.
This standard applies to grid-connected wind turbines.
2 Normative references
The following documents are indispensable for the application of this document. For dated references, only dated versions apply to this document. For undated references, the latest edition (including all amendments) applies to this document.
JJF1059.1 Measurement Uncertainty Evaluation and Representation
3 Terms and definitions
The following terms and definitions apply to this document.
3.1 Wind turbine low voltage ride through capability
When the power grid fails or the disturbance causes a voltage drop, the wind turbine ensures that it does not fall off the network within a certain voltage drop range and time interval. The ability to continue running.
3.2 Wind turbine high voltage ride through capability
When the grid fault or disturbance causes the voltage to rise, within a certain range of voltage rise and time interval, the wind turbine guarantees that there is no off-grid The ability to continue running.
3.3 Fault voltage generating device
Based on the impedance/resistance-capacitor voltage division principle, test equipment that meets the test requirements for fault voltage specifications is generated at the test point.
3.4 Grid point/test point
The point at which the fault voltage is generated is the connection point between the fault voltage generating device and the high voltage side of the step-up transformer of the wind turbine.
3.5 Active power recovery time
From the recovery of the grid voltage to the normal range, to the wind turbine output active power is restored to the actual wind condition corresponding to the output power required time.
3.6 Voltage drop
The effective value of the voltage at a certain point in the power system is temporarily reduced to less than 0.9 pu of the nominal voltage of the system, and returns to normal after a short duration. A phenomenon near the value.
......
This preview omits tables, figures, formulas and parts of the technical clauses. The complete document — 20 pages — is available in the English PDF.
Referenced standards
Cited by
- GB/T 43904-2024Wind energy generation systems - Operation evaluation index system for wind turbines
- GB/T 44908-2024Safety requirements and evaluation methods for technical transformation of wind farm
- GB/T 25386.2-2021Wind turbines—Control system—Part 2: Test method
- GB/T 25387.2-2021Wind turbines generator system—Full-power converter—Part 2:Test method
- GB/T 25388.2-2021Wind turbines generator system—Double-fed converter—Part 2: Test method
- GB/T 40082-2021Wind turbines—Drive train ground test specification
Similar standards
How to Download GB/T 36995-2018
- 1
Add to cart
Click "Download PDF" on this page and choose "Buy this standard". You can add more standards before checkout.
- 2
Checkout
Enter your email and billing details. Payment is processed securely by Stripe (cards or bank transfer). Prefer bank details? Request a quotation (min. order $300).
- 3
Instant delivery (0–9 sec)
Delivery is automatic: within seconds of payment you'll receive an email with a secure download link. The link stays valid for 72 hours.
- 4
Invoice included
A tax invoice is attached to the confirmation email. Need a custom invoice? Contact us.
Related Standards
GB/T 10003-2026 — Biaxially oriented polypropylene (BOPP) film
GB/T 10004-2026 — Plastic/Plastic laminated films and pouches for packaging
GB/T 10007-2026 — Rigid cellular plastics - Determination of shear properties
Secure payment via Stripe
Payments accepted
GB/T 36995-2018
$360.00