Valid

GB/T 42398-2023Technical specifications of cleanroom design for cell culture (English PDF)

细胞培养洁净室设计技术规范

Open the GB/T 42398-2023 preview as PDF

Preview — first pages of GB/T 42398-2023 (full document: 18 pages)

This is a limited preview

Buy now to download the full PDF (18 pages)

Issued by

SAMR; SAC

Level / Type

National · Recommended

Issue date

March 17, 2023

Implementation date

October 1, 2023

Scope

GB/T 42398-2023 is the English-translated version of 细胞培养洁净室设计技术规范.

GB/T 42398-2023 covers the design of a cleanroom in which cells taken from an organism are grown, expanded and kept with their biological properties intact. Almost the whole document sits in a single requirements clause, and it works outward from the ground: site selection, then ventilation and purification, the envelope structure, electrical and information technology services, water supply and drainage, gas pipelines, and the safety requirements that apply to the finished suite. Terms are defined narrowly, cell culture among them, because the room is specified around the process rather than around a particle count alone. The services are treated as one design instead of as separate trades because a cell culture room fails differently from an ordinary cleanroom: the contamination that ruins the work is alive, an organism carried in on air, on a surface or back through a drain multiplies in exactly the warm, humid conditions the culture needs, and what is lost is not a rejected batch but a cell line and the months of work behind it. Pressure regime, air change, sealed penetrations, drainage routes and the gas lines feeding the incubators therefore stand or fall together. For laboratory and facility designers, HVAC contractors, cell therapy and biopharmaceutical manufacturers, and the people who qualify such rooms before use.

Document preview — GB/T 42398-2023

National Standard of the People's Republic of China

ICS
13.040.35
Classification
C70

Issued by: State Administration for Market Regulation; Standardization Administration of the PRC

Contents

  • Foreword3
  • Introduction5
  • 1 Scope6
  • 2 Normative references6
  • 3 Terms and definitions6
  • 4 Requirements8
  • Bibliography18

Foreword

This document was issued on 17 March 2023 by the State Administration for Market Regulation; Standardization Administration of the PRC and takes effect on 1 October 2023.

It is a GB/T standard: recommended rather than compulsory, but it is the text a Chinese reviewer applies when assessing a submission.

1 Scope

GB/T 42398-2023 covers the design of a cleanroom in which cells taken from an organism are grown, expanded and kept with their biological properties intact. Almost the whole document sits in a single requirements clause, and it works outward from the ground: site selection, then ventilation and purification, the envelope structure, electrical and information technology services, water supply and drainage, gas pipelines, and the safety requirements that apply to the finished suite. Terms are defined narrowly, cell culture among them, because the room is specified around the process rather than around a particle count alone. The services are treated as one design instead of as separate trades because a cell culture room fails differently from an ordinary cleanroom: the contamination that ruins the work is alive, an organism carried in on air, on a surface or back through a drain multiplies in exactly the warm, humid conditions the culture needs, and what is lost is not a rejected batch but a cell line and the months of work behind it. Pressure regime, air change, sealed penetrations, drainage routes and the gas lines feeding the incubators therefore stand or fall together. For laboratory and facility designers, HVAC contractors, cell therapy and biopharmaceutical manufacturers, and the people who qualify such rooms before use.

This document specifies the general requirements for cleanroom design for cell culture,

ventilation and purification, enclosure structure, electrical and information technology,

water supply and drainage, gas pipelines, and safety requirements.

This document applies to cleanroom design for cell culture for human use. Other cell

culture cleanrooms refer to this document.

2 Normative references

The following referenced documents are indispensable for the application of this

document. For dated references, only the edition cited applies. For undated references,

the latest edition of the referenced document (including any amendments) applies.

GB 5749, Sanitary standard for drinking water

GB 17945, Fire Emergency Luminaries

GB/T 29469, Cleanrooms and associated controlled environments - Evaluation of

performance and rationality

GB/T 36372, Cleanrooms and associated controlled environments - General

technical requirements of combined envelope structure

GB 50016, Code of Design on Building Fire Protection and Prevention

GB 50457, Code for design of pharmaceutical industry cleanroom

GB 50472, Code for design of electronic industry cleanroom

GB 50591, Code for Construction and Acceptance of Cleanroom

3 Terms and definitions

For the purposes of this document, the following terms and definitions apply.

3.1 cell culture

A process of growing, expanding, and maintaining the biological properties of extracted

cells.

4 Requirements

4.1 General requirements

4.1.1 The design of site selection, ventilation and purification, envelope structure,

electrical and information technology, water supply and drainage, gas pipelines, safety

and other aspects shall be carried out in combination with the cell culture process and

environmental requirements.

4.1.2 An area with less vibration, electromagnetic radiation, and noise shall be selected.

When the area of a new cleanroom is greater than or equal to 3000 m2, while meeting

the above requirements, the building where it is located shall be selected in an area with

good natural environment and low gas pollution.

4.1.3 When the area of a newly built, renovated or expanded cleanroom is greater than

or equal to 3000 m2, the design of the cleanroom shall be closely connected with the

overall design of the building where it is located. After negotiating with the user to

determine the process requirements and cleanroom location, the design will be

prioritized based on consultation with the overall design. Propose requirements for

building structure, power, HVAC, water supply and drainage, electrical and other

aspects to the overall design.

4.1.4 Full consideration shall be given to preparation process flow, equipment

configuration, safety and reliability of equipment and facilities, various interfaces, flow

of people, logistics, storage of items (necessary) in-situ inactivation and disinfection of

hazardous waste products, construction and installation, equipment installation,

inspection and maintenance and other related requirements.

4.1.5 The cleanliness and other relevant requirements of each area shall comply with

4.2.

4.1.6 The purpose shall be to protect personal safety. Consider a plan to evacuate

cleanroom staff as soon as possible in an emergency and minimize damage to the

cleanroom and support areas.

4.1.7 On the basis of meeting the process requirements and operating cycle, it shall

focus on saving energy, protecting the environment, and being economically reasonable.

4.1.8 When the cleanroom area is greater than or equal to 2000 m2, the design evaluation

shall be carried out in accordance with the requirements of GB/T 29469. If the area is

less than 2000 m2, it can choose whether to conduct design evaluation.

4.1.9 For cleanrooms containing cell cultures carrying infectious agents, a biosafety

plan shall be developed based on risk assessment. Ensure that its production and

operation process does not cause pollution or harm to personnel and the environment.

Avoid cross contamination.

humidity loads of various equipment within the system need to be considered at the

same time).

NOTE: Pay attention to extreme climates, especially the demand for cold and heat sources with

sustained extreme temperatures and humidity.

4.3.1.3 The division of purification air-conditioning systems shall be determined after

technical and economic comparison based on process requirements, floor plan,

biological safety, etc. Take effective measures to avoid contamination and cross-

contamination. Meet the following requirements:

a) The air conditioning system shall be set up separately from areas without

cleanliness requirements.

b) Production units with different process requirements shall be equipped with

separate purification and air-conditioning systems.

c) Functional areas with different operating shifts or usage times shall be equipped

with separate purification and air-conditioning systems.

d) In areas with large differences in indoor heat and moisture load characteristics,

separate purification air conditioning systems shall be installed.

4.3.1.4 When there are ventilation equipment such as biological safety cabinets and

local exhaust devices in the cleanroom, measures shall be taken to maintain indoor

pressure stability during the opening, closing and operation of the equipment.

4.3.1.5 It must be conducive to cleanroom disinfection, sterilization, automatic control

and energy-saving operation. Comply with the following regulations:

a) Positive pressure cleanrooms shall use circulating air conditioning systems.

b) When toxic, harmful, or combustible gases are involved (excluding cell culture

areas carrying infectious agents), a partial or overall full exhaust system shall be

adopted based on risk assessment.

c) Measures shall be taken to dilute and replace room gas after disinfection and

sterilization.

4.3.1.6 The design of the cleanroom exhaust system meets the following requirements:

a) The exhaust systems of different purification air-conditioning systems shall be set

up independently.

b) When harmful substances, odors, large amounts of heat, moisture or volatile gases

are produced, a separate exhaust system shall be set up.

c) Measures shall be taken to prevent the infiltration of outdoor gas.

d) For exhaust systems containing water vapor and condensable substances, a slope

shall be set. Set up a discharge port at the local lowest point of the pipeline.

4.3.1.7 For air conditioning systems that use circulating air, a primary (medium)

efficiency air filter shall be installed at the return air outlet of the cleanroom as

appropriate.

4.3.1.8 The opening and closing of the supply air, return air and exhaust air of the

purification air conditioning system shall be interlocked and comply with the following

regulations:

a) The chain procedure of the positive pressure cleanroom is to start the air supply

fan first, then start the return air fan (if any) and exhaust fan. The chain procedure

shall be reversed when closing.

b) The chain procedure of the negative pressure cleanroom is to start the return air

fan and exhaust fan (if any) first, and then start the air supply fan. The chain

procedure shall be reversed when closing.

4.3.2 Airflow organization

4.3.2.1 Airflow complies with the following regulations:

a) The clean area shall adopt a one-way flow pattern.

b) Areas outside the clean area may use non-unidirectional flow patterns. Non-

unidirectional flow patterns need to reduce the vortex area.

c) Airflow distribution shall be even. The air flow rate shall meet the requirements

of production technology and human hygiene.

4.3.2.2 When setting up a unidirectional flow workbench in a non-unidirectional flow

cleanroom, its location shall avoid being close to the air supply and return vents.

4.3.2.3 If there is a local exhaust device, it shall be arranged on the downwind side of

the cleanroom (area).

4.3.3 Parts and materials

They shall comply with the relevant requirements of GB 50457 and GB 50591.

4.3.4 Special requirements for cell culture areas carrying infectious agents

4.3.4.1 Biosafety plans for various working conditions in the area (operating or not,

entry and exit of equipment and facilities, maintenance, troubleshooting, etc.) shall be

jointly developed with relevant process personnel.

4.3.4.2 The cell culture area carrying the virus and the adjacent room or area shall

maintain a negative pressure. The pressure difference shall not be less than 10 Pa.

GB 50016.

4.5.2 Illumination

4.5.2.1 Lighting fixtures shall be dedicated to cleanrooms. The maintenance and

replacement of lamps shall avoid adverse effects on the cleanroom environment.

4.5.2.2 The illumination and illumination uniformity of each area meet the requirements

of Table 3.

4.5.2.3 Emergency lighting and evacuation lighting shall be set up. It shall comply with

the regulations of GB 17945.

4.5.3 Intelligent information system

4.5.3.1 Fire safety emergency broadcasts shall be set up.

4.5.3.2 The following terms apply to cell culture cleanrooms with intelligent

information requirements.

4.5.3.3 The architecture and system configuration shall meet the requirements of

business systems and management systems for network segmentation. Information

security requirements for network physical isolation and logical isolation shall be met.

It shall meet energy-related functional requirements. Improve operational efficiency,

reliability and safety.

4.5.3.4 Communication interfaces and protocols that are open and comply with

international and current national standards shall be provided.

4.5.3.5 The user operation interface shall be able to be set according to usage

requirements.

4.5.3.6 A monitoring system for controlled environmental parameters shall be set up.

4.5.3.7 A closed-circuit television surveillance system can be set up according to the

requirements of production management and production technology, which can watch

and record the entire process in real time from multiple angles and without blind spots.

NOTE: The automatic monitoring device is installed on the ceiling.

4.5.3.8 The access control management system shall be set up according to functional

partitions. The access control management system shall realize linkage control with the

emergency escape and automatic fire alarm systems. The access control system shall be

automatically deactivated in the event of an emergency or fire. Ensure that emergency

escape routes are clear during evacuation.

4.5.3.9 There shall be a communication system to facilitate contact with relevant

departments.

4.5.3.10 When using flammable, explosive and other dangerous media, corresponding

monitoring and alarm devices shall be set up indoors and in the monitoring room.

NOTE: Subclauses 4.5.1 and 4.5.3 are applicable to pharmaceutical and cell culture cleanrooms

used for cell therapy.

4.6 Drainage

4.6.1 General provisions

4.6.1.1 It shall comply with the relevant requirements of GB 50472 and GB 50457.

4.6.1.2 Casings shall be installed where the water supply and drainage branch pipes

pass through the ceiling, walls and floors of the cleanroom. There shall be reliable

sealing measures between pipes and sleeves.

4.6.1.3 Measures shall be taken to prevent condensation and burns on the outer surface

of the pipe.

NOTE: This article applies to pharmaceutical and cell culture cleanrooms used for cell therapy.

4.6.2 Water supply

4.6.2.1 Water quality shall comply with the requirements of GB 5749.

4.6.2.2 Water supply pipes and accessories shall be corrosion-resistant and easy to

install and connect.

4.6.3 Drainage

4.6.3.1 The drainage system shall be determined based on the characteristics,

concentration and volume of discharged wastewater.

4.6.3.2 The drainage equipment in the cleanroom and the equipment connected to the

gravity return pipe shall be equipped with a water sealing device below the discharge

outlet. The water seal height shall not be less than 50 mm. Drainage outlets of process

equipment shall be equipped with air blocking devices. The drainage system shall have

a complete ventilation system.

4.6.3.3 The drainage riser shall not pass through a cleanroom with a cleanliness level

higher than or equal to ISO 6 and its corresponding level. There shall be no inspection

opening when the drainage riser passes through other cleanrooms.

4.6.3.4 Floor drains shall not be installed in ISO levels 5, 6 and corresponding

cleanrooms. If a cleanroom lower than the above-mentioned requirements must be

installed, the floor drain must be made of material that is not prone to corrosion, has a

smooth inner surface, is not prone to scaling, has a sealing cover, is easy to open, must

be resistant to sterilization, and can prevent the backflow of waste water and gas.

......

......
This preview omits tables, figures, formulas and parts of the technical clauses. The complete document — 18 pages — is available in the English PDF.

Referenced standards

Similar standards

How to Buy GB/T 42398-2023

  1. 1Add to cart. Click the "Buy GB/T 42398-2023" button on this page. You can add more standards before checkout.
  2. 2Checkout. Enter your email and billing details. Payment is processed securely by Stripe (cards, Apple Pay, Google Pay supported).
  3. 3Instant delivery (0–9 sec). Delivery is automatic: within seconds of payment you'll receive an email with a secure download link. The link stays valid for 72 hours.
  4. 4Invoice included. A tax invoice is attached to the confirmation email. Need a custom invoice? Contact us.

Related Standards

English PDF
18 pages
Instant delivery (0–9 sec)
Invoice included
View Cart

Secure payment via Stripe

Payments accepted

VisaMastercardAmerican ExpressApple PayGoogle PayStripe

GB/T 42398-2023

$245.00

$210.00for partners