GB/T 26471-2023Tower crane—Rules of installation, disassembly and climbing (English PDF)
塔式起重机 安装、拆卸与爬升规则
This is a limited preview
Buy now to download the full PDF (15 pages)
Need quotation for your management?
Get a formal quotation for GB/T 26471-2023 in 30 minutes.
Issued by
SAMR; SAC
Level / Type
National · Recommended
Issue date
March 17, 2023
Implementation date
October 1, 2023
Scope
GB/T 26471-2023 is the English-translated version of 塔式起重机 安装、拆卸与爬升规则.
GB/T 26471-2023 is the Chinese national rulebook for erecting, dismantling and climbing a tower crane.
It sets the requirements for the units and the personnel who do the work, the basic provisions for installation and dismantling, the preparations beforehand, the work up to the basic erection height, the climbing of an external-climbing crane, the fitting and removal of attachment devices, the internal-climbing or externally hung crane, the commissioning of the safety protection devices and the inspection and acceptance once the crane stands.
Table 1 gives the safe distance between crane and overhead power line. It applies to assembled top-slewing tower cranes, other types following it by reference, and it does not cover self-erecting or mobile self-erecting cranes.
It replaces GB/T 26471-2011, was issued on 17 March 2023 and has applied since 1 October 2023.
Found what you need?
Document preview — GB/T 26471-2023
National Standard of the People's Republic of China
- ICS
- 53.020.20
- Classification
- J 80
- Replacing
- GB/T 26471-2011
Issued by: State Administration for Market Regulation; Standardization Administration of the PRC
Contents
- Preface
- 1 Scope
- 2 Normative references
- 3 Terms and Definitions
- 4 Installation and dismantling units and personnel
- 5 Basic regulations for installation and dismantling
- 6 Preparations before installation and disassembly
- 7 Installation and disassembly of basic erection height
- 8 Climbing operation of external climbing tower crane
- 9 Installation and removal of attachment devices
- 10 Installation and disassembly of internal climbing (external hanging) tower crane
- 11 Commissioning of safety protection devices
- 12 Inspection and acceptance after installation
- Reference
Foreword
This document is in accordance with the provisions of GB/T 1.1-2020 "Guidelines for Standardization Work Part 1: Structure and Drafting Rules for Standardization Documents" drafting.
This document replaces GB/T 26471-2011 "Rules for Installation and Disassembly of Tower Cranes". Compared with GB/T 26471-2011, except Apart from structural adjustments and editorial changes, the main technical changes are as follows:
---Changed and added some terms and definitions (see Chapter 3, Chapter 3 of the 2011 edition);
--- Deleted the term definition of "transition section" (see 3.2 of the 2011 edition);
---Change and increase the requirements for installation and disassembly units and personnel (see Chapter 4, Chapter 4 of the 2011 edition);
--- Increased requirements for special programs (see 5.2);
---Changed and added the requirements for installation and dismantling safety distance and group tower operation installation safety distance (see 5.4, 5.5, 5.4~5.6 of the 2011 edition);
--- Added requirements for installation site selection (see 5.6);
--- Increased post-installation self-test and debugging requirements (see 5.7.1);
--- Added the requirements for inspection and acceptance after installation self-inspection (see 5.7.2);
--- Added requirements for windshields, warning signs and components (see 5.8);
--- Added the requirements for technical disclosure before installation and disassembly (see 6.1.4);
--- Increased the requirements for staffing on-site installation and dismantling (see 6.2);
--- Changed the inspection requirements before installation (see 6.4.1, 6.3.1 of the 2011 edition);
---Changed the requirements on the foundation and attached buildings (structures) (see 6.5, 6.4 of the 2011 edition);
--- Increased the verticality requirements of the tower body in the no-load state (see 7.4);
--- Changed the requirements for high-strength bolts (see 7.6, 7.5 of the 2011 edition);
--- Added the requirements for the installation of the jib tie rod (see 7.12);
--- Added the requirements for the total installation height of the internal climbing (external hanging) tower crane and the installation position of the special frame (see 7.13);
--- Added the requirements for commissioning of the working mechanism and wiring of the electrical system after installation (see 7.14, 7.15);
--- Added requirements for disassembly process (see 7.16);
--- Increased the basic erection height stage inspection and testing requirements (see 7.18);
--- Increased the balance requirements for the climbing part of the tower crane (see 8.2.4);
--- Increased the requirements on the reduction of knots (see 8.2.7);
--- Changed the requirements on the hydraulic system (see 8.3, 8.3 of the 2011 edition);
--- Added design and manufacture requirements for non-standard attachment devices (see 9.1.3);
--- Increase the design and manufacture requirements for non-standard components of internal climbing (external hanging) tower cranes (see 10.1.1);
---Changed the requirements for dismantling the internal climbing (external hanging) tower crane (see 10.3, 10.3 of the 2011 edition).
1 Scope
This document specifies the installation, dismantling and climbing (hereinafter referred to as "installation and disassembly") operations of tower cranes (hereinafter referred to as "tower cranes").
Units and personnel, basic regulations for installation and dismantling, preparations before installation and dismantling, installation and dismantling of basic erection heights, climbing operations of external climbing tower cranes, installation and removal of attachment devices Requirements for installation and disassembly, installation and disassembly of internal climbing (external hanging) tower cranes, commissioning of safety protection devices, inspection and acceptance after installation.
This document is applicable to the installation and dismantling of assembled upper-slewing tower cranes, and the installation and dismantling of other types of tower cranes shall be carried out by reference.
Note: This document gives suggestions and guidance on the management of tower crane installation and dismantling operations, including the responsibilities of the user unit and supplier unit involved in these operations, and relevant personnel. responsibilities and conditions of employment.
This document does not apply to the installation and dismantling of self-erecting tower cranes and mobile self-erecting tower cranes.
2 Normative references
The contents of the following documents constitute the essential provisions of this document through normative references in the text. Among them, dated references For documents, only the version corresponding to the date is applicable to this document; for undated reference documents, the latest version (including all amendments) is applicable to this document.
GB/T 5031-2019 Tower Cranes
GB 5144-2006 Safety regulations for tower cranes
GB/T 6974.3 Crane Terminology Part 3: Tower Cranes
GB/T 23723.3-2010 Safe use of cranes Part 3: Tower cranes
GB/T 23724.3-2010 Crane Inspection Part 3: Tower Cranes
GB/T 31052.3-2016 Inspection and Maintenance Procedures for Lifting Machinery Part 3: Tower Cranes
GB/T 33080-2016 Safety Assessment Procedures for Tower Cranes
GB 50169 Specifications for construction and acceptance of grounding devices for electrical installation engineering
JB/T 13915 Pre-tightening and anti-loosening of high-strength bolts for tower cranes
3 Terms and Definitions
The following terms and definitions defined in GB/T 6974.3 and GB/T 5031-2019 apply to this document.
3.1 Basic erection height
Before the tower crane is installed and climbed for the first time, from the top surface of the foundation that supports the tower body of the tower crane or the top surface of the track of the walking tower crane to the hinge at the root of the boom The minimum height of the point.
3.2 Cast-in base
In-situ poured reinforced concrete foundation for fixing or installing tower crane underframe, feet or embedded joints.
3.3 Assembled base
The specially designed concrete prefabricated parts are assembled into a whole through the assembled connecting cable, which is used to transmit the load of the tower crane to the foundation of the foundation.
......
This preview omits tables, figures, formulas and parts of the technical clauses. The complete document — 15 pages — is available in the English PDF.
Referenced standards
Normative references
- GB/T 5031-2019Tower cranes
- GB 5144-2006Safety code for tower cranes
- GB/T 6974.3Cranes - Vocabulary - Part 3: Tower cranes
- GB/T 23723.3-2010Cranes -- Safe use -- Part 3: Tower cranes
- GB/T 23724.3-2010Cranes - Inspections - Part 3: Tower cranes
- GB/T 31052.3-2016Lifting appliances—Code of inspection and maintenance—Part 3: Tower cranes
GB 50169
Similar standards
Editions of GB/T 26471
| Edition | Title | Revision | Status |
|---|---|---|---|
| GB/T 26471-2023 | Tower crane—Rules of installation, disassembly and climbing | current edition | Current |
| GB/T 26471-2011 | Tower crane—Rules of installation, disassembly and climbing | previous edition | Superseded |
This page sells the current edition, GB/T 26471-2023. Earlier editions are listed for reference only.
How to Download GB/T 26471-2023
- 1
Add to cart
Click "Download PDF" on this page and choose "Buy this standard". You can add more standards before checkout.
- 2
Checkout
Enter your email and billing details. Payment is processed securely by Stripe (cards or bank transfer). Prefer bank details? Request a quotation (min. order $300).
- 3
Instant delivery (0–9 sec)
Delivery is automatic: within seconds of payment you'll receive an email with a secure download link. The link stays valid for 72 hours.
- 4
Invoice included
A tax invoice is attached to the confirmation email. Need a custom invoice? Contact us.
Related Standards
GB 5144-2006 — Safety code for tower cranes
GB/T 23723.3-2010 — Cranes -- Safe use -- Part 3: Tower cranes
GB/T 31052.3-2016 — Lifting appliances—Code of inspection and maintenance—Part 3: Tower cranes
Secure payment via Stripe
Payments accepted
GB/T 26471-2023
$270.00