NB/T 20100-2016Requirements of overpressure analysis for reactor coolant system and main steam system for pressurized water reactor nuclear power plants (English PDF)
压水堆核电厂反应堆冷却剂系统和主蒸汽系统超压分析要求
This is a limited preview
Buy now to download the full PDF (15 pages)
Need quotation for your management?
Get a formal quotation for NB/T 20100-2016 in 30 minutes.
Issued by
NEA
Level / Type
Industry · Recommended
Issue date
February 5, 2016
Implementation date
July 1, 2016
Scope
NB/T 20100-2016 is the English-translated version of 压水堆核电厂反应堆冷却剂系统和主蒸汽系统超压分析要求.
NB/T 20100-2016 is the Chinese standard "Requirements of overpressure analysis for reactor coolant system and main steam system for pressurized water reactor nuclear power plants".
Its scope clause reads: This standard specifies the basic requirements of overpressure analysis for reactor coolant system and main steam system for pressurized water reactor nuclear power plants.
This standard is applicable to the overpressure analysis for reactor coolant system and main steam system for pressurized water reactor nuclear power plants. Its clauses include terms and definitions.
Found what you need?
Document preview — NB/T 20100-2016
National Standard of the People's Republic of China
- ICS
- 27.120.20
- Replacing
- NB/T 20100-2012
Issued by: National Energy Administration of the People's Republic of China
Contents
- Foreword i
- 1 Scope
- 2 Normative references
- 3 Terms and definitions
- 4 Requirements for overpressure analysis of power operation condition
- 5 Requirements for low temperature overpressure analysis
- 6 Criteria for overpressure analysis
1 Scope
This standard specifies the basic requirements of overpressure analysis for reactor coolant system and main steam system for pressurized water reactor nuclear power plants.
This standard is applicable to the overpressure analysis for reactor coolant system and main steam system for pressurized water reactor nuclear power plants.
2 Normative references
The following referenced documents are indispensable for the application of this document. For dated references, only the edition cited applies. For undated references, the latest edition of the referenced document (including any amendments) applies.
NB/T 20035-2011 (2014RK) Categorization of conditions of PWR nuclear power plants
NB/T 20104 Analysis requirements for anticipated transient without scram on pressurized water reactor nuclear power pants
3 Terms and definitions
For the purposes of this document, the following terms and definitions apply.
3.1 condition II
possible deviation from normal operation or fault of a nuclear power unit within one calendar year
3.2 condition III
event that may occur during the service life of a nuclear power unit but at a very low frequency
3.3 condition IV
hypothetical accident that is unlikely to occur during the service life of a nuclear power unit but shall be provided with targeted design measures
3.4 reactor coolant system
circulating system for transferring heat generated by the reactor core to the secondary side of steam generator
3.5 main steam system
system for transferring steam from the steam generator to other equipment, consisting of secondary side of steam generator, main steam pipe, main steam atmospheric relief valve, main steam safety valve, main steam isolation valve, etc.
3.6 reactor coolant system pressure boundary
outermost physical boundary that contains reactor coolant and bears system design pressure and design temperature, usually limited to the first isolation valve that connects the auxiliary system pipe with the main pipeline
3.7 anticipated transients without scram (ATWS)
anticipated event that occurs in the nuclear power plants and changes the reactor physical and thermal parameters to the shutdown thresholds, without reactor shutdown when subsequent automatic shutdown is required (also referred to as ATWS)
3.8 water solid
status in which reactor has been shut down, the residual heat removal system is put into operation and the pressurizer is full of water
3.9 low temperature overpressure
system overpressure that may be caused by energy injection or mass injection when the reactor coolant system is at low temperature and the pressurizer is in a water solid status […]
......
This preview omits tables, figures, formulas and parts of the technical clauses. The complete document — 15 pages — is available in the English PDF.
Referenced standards
Normative references
Similar standards
Editions of NB/T 20100
| Edition | Title | Revision | Status |
|---|---|---|---|
| NB/T 20100-2016 | Requirements of overpressure analysis for reactor coolant system and main steam system for pressurized water reactor nuclear power plants | current edition | Current |
| NB/T 20100-2012 | Requirements of overpressure analysis for reactor coolant system and main steam system for pressurized water reactor nuclear power plants | previous edition | Superseded |
This page sells the current edition, NB/T 20100-2016. Earlier editions are listed for reference only.
How to Download NB/T 20100-2016
- 1
Add to cart
Click "Download PDF" on this page and choose "Buy this standard". You can add more standards before checkout.
- 2
Checkout
Enter your email and billing details. Payment is processed securely by Stripe (cards or bank transfer). Prefer bank details? Request a quotation (min. order $300).
- 3
Instant delivery (0–9 sec)
Delivery is automatic: within seconds of payment you'll receive an email with a secure download link. The link stays valid for 72 hours.
- 4
Invoice included
A tax invoice is attached to the confirmation email. Need a custom invoice? Contact us.
Related Standards
NB/T 20035-2011 — Categorization of Conditions of PWR Nuclear Power Plants
NB/T 20104-2012 — Analysis Requirement for Anticipated Transient without Scram on Pressurized Water Reactor Nuclear Power Plants
NB/T 10086-2025 — Regulations for Compiling Energy Conservation Reports for Wind Farm Projects
Secure payment via Stripe
Payments accepted
NB/T 20100-2016
$135.00