GB/T 38957-2020Technical specification for effect evaluation of tropical cyclone on offshore wind power project (English PDF)

海上风电场热带气旋影响评估技术规范

Preview PDF

This is a limited preview

Buy now to download the full PDF (15 pages)

Need quotation for your management?

Get a formal quotation for GB/T 38957-2020 in 30 minutes.

Issued by

SAMR; SAC

Level / Type

National · Recommended

Issue date

July 21, 2020

Implementation date

July 21, 2020

Scope

GB/T 38957-2020 is the English-translated version of 海上风电场热带气旋影响评估技术规范.

GB/T 38957-2020 is the Chinese standard "Technical specification for effect evaluation of tropical cyclone on offshore wind power project".

Its scope clause reads: This standard specifies the determination of tropical cyclone impact assessment areas, data collection and processing, tropical cyclone risk assessment and tropical cyclone risk assessment for offshore wind farms.

Technical methods for benefit evaluation of cyclone power generation. This standard applies to tropical cyclone risk assessment and power generation benefit assessment for offshore wind power development. Its clauses include terms and definitions.

Found what you need?

Document preview — GB/T 38957-2020

National Standard of the People's Republic of China

ICS
07.060
Classification
A 47

Issued by: State Administration for Market Regulation; Standardization Administration of the PRC

Contents

  • 1 Scope1
  • 2 Normative references1
  • 3 Terms and definitions1
  • 4 Determination of assessment area3
  • 5 Data collection and processing3
  • 6 Tropical cyclone risk assessment3
  • 7 Evaluation of the benefits of tropical cyclone power generation5
  • Appendix A (Normative Appendix) Wind speed calculation at hub height under standard air density6
  • Appendix B (Normative Appendix) Poisson-Gumbel distribution affected by tropical cyclones7

1 Scope

This standard specifies the determination of tropical cyclone impact assessment areas, data collection and processing, tropical cyclone risk assessment and tropical cyclone risk assessment for offshore wind farms.

Technical methods for benefit evaluation of cyclone power generation.

This standard applies to tropical cyclone risk assessment and power generation benefit assessment for offshore wind power development.

2 Normative references

The following documents are indispensable for the application of this document. For dated reference documents, only the dated version applies to this article

Pieces. For undated references, the latest version (including all amendments) applies to this document.

GB/T 31519-2015 Typhoon wind turbine

GB/T 36745-2018 Typhoon Vortex Wind Data Discrimination Specification

NB/T 31147-2018 Technical Specification for Wind Energy Resource Measurement and Evaluation of Wind Farm Project

QX/T 438-2018 Bridge Design Wind Speed Calculation Code

IEC 61400-1.2019 Wind energy generation systems-Part 1.Design requirements (Windenergygenerationsystems-Part 1.

Designrequirements)

3 Terms and definitions

The following terms and definitions apply to this document.

3.1 Offshorewindpowerproject

Wind farms are developed and constructed in the sea areas below the average high tide line of the coast for many years and on islands without residents in the corresponding development sea areas.

Note. Rewrite NB/T 31029-2012, definition 2.0.3.

3.2 Tropical cyclone

Generated on the surface of tropical or subtropical oceans, there are non-frontal vortices with organized convection and definite cyclonic circulation.

Note 1.Including tropical depression, tropical storm, strong tropical storm, typhoon, strong typhoon and super typhoon.

Note 2.Rewrite GB/T 19201-2006, definition 2.1.

3.3 Engineeringarea

A closed sea area composed of several control points on the periphery of an offshore wind farm.

3.4 Evaluationofthebenefitsoftropicalcycloneenergyproduction

Evaluation of power generation efficiency in the peripheral wind area of tropical cyclones that meets the power generation conditions of wind turbines.

3.5 Evaluationarea

Extend a certain range beyond the boundary of the project area to be used for risk assessment or benefit assessment.

......
This preview omits tables, figures, formulas and parts of the technical clauses. The complete document — 15 pages — is available in the English PDF.

Similar standards

How to Download GB/T 38957-2020

  1. 1

    Add to cart

    Click "Download PDF" on this page and choose "Buy this standard". You can add more standards before checkout.

  2. 2

    Checkout

    Enter your email and billing details. Payment is processed securely by Stripe (cards or bank transfer). Prefer bank details? Request a quotation (min. order $300).

  3. 3

    Fast delivery

    After payment you'll receive an email confirmation. The English PDF is sent to the same address, usually within minutes and at the latest within 1 business day.

  4. 4

    Invoice included

    A tax invoice is attached to the confirmation email. Need a custom invoice? Contact us.

Related Standards

English PDF
15 pages
Fast delivery
Invoice included
View Cart

Secure payment via Stripe

Payments accepted

VisaMastercardAmerican ExpressApple PayGoogle PayStripe

GB/T 38957-2020

$210.00