Valid

GB/T 38334-2019Technical specification for black-start of hydropower station (English PDF)

水电站黑启动技术规范

Preview PDF

This is a limited preview

Buy now to download the full PDF (17 pages)

Need quotation for your management?

Get a formal quotation for GB/T 38334-2019 in 30 minutes.

Issued by

SAMR; SAC

Level / Type

National · Recommended

Issue date

December 10, 2019

Implementation date

July 1, 2020

Scope

GB/T 38334-2019 is the English-translated version of 水电站黑启动技术规范.

GB/T 38334-2019 specifies the general rules, the basic technical conditions, the black-start tests, the black-start procedures and the emergency treatment for the black start of hydropower stations.

Clause 1 states that it applies to hydropower stations with black start capability, and writes no exclusion.

The contents list runs from clause 4, General, through clause 5, Basic technical conditions, which is split into Class A black start and Class B black start, clause 6, Black start test, which covers general requirements, the equipment system test, the black start power test, the phased test, the overall test and black start mode identification, and clause 7, Black start procedures and emergency response.

Five appendices follow, on a typical black start load statistics table, the tests to be performed during black start, the calculation of battery discharge time, a black start overall test data record and an example of a black-start procedure; only the second of them is marked normative.

Clause 3 defines six terms, among them the black-start power supply, the Class A and Class B black-start modes and the black start of a hydropower station, the Class A mode using only the electric energy stored in the DC battery and the hydraulic energy stored in the hydraulic system to restore the working power of the plant.

Clause 2 cites GB/T 2820.5, GB/T 9652.2, DL/T 583, DL/T 724 and NB/T 35044. The foreword states that the standard is proposed and managed by the China Electric Power Enterprise Federation. It was issued on 2019-12-10 and has applied since 2020-07-01.

Found what you need?

Document preview — GB/T 38334-2019

National Standard of the People's Republic of China

ICS
27.140
Classification
K 55

Issued by: State Administration for Market Regulation; Standardization Administration of the PRC

Contents

  • Foreword
  • 1 Scope
  • 2 Normative references
  • 3 Terms and definitions
  • 4 General
  • 5 Basic technical conditions
  • 5.1 Class A Black Start
  • 5.2 Class B Black Start
  • 6 Black Start Test
  • 6.1 General requirements
  • 6.2 Equipment system test
  • 6.3 Black start power test
  • 6.4 Phased test
  • 6.5 Overall test
  • 6.6 Black Start Mode Identification
  • 7 Black start procedures and emergency response
  • 7.1 Black Start Program
  • 7.2 Emergency treatment
  • Appendix A (Informative) Typical Black Start Load Statistics Table
  • Appendix B (Normative) Tests to be performed during black start
  • Appendix C (informative) Calculation of battery discharge time
  • Appendix D (Informative) Black Start Overall Test Data Record
  • Appendix E (informative) Example of a black-start procedure

Foreword

This standard was drafted in accordance with the rules given in GB/T 1.1-2009.

1 Scope

This standard specifies the general rules, basic technical conditions, black-start tests, black-start procedures, and emergency treatment of hydropower stations.

This standard applies to hydropower stations with black start capability.

2 Normative references

The following documents are essential for the application of this document. For dated references, only the dated version applies to this document. For undated references, the latest version (including all amendments) applies to this document.

GB/T 2820.5 AC generator set driven by reciprocating internal combustion engine-Part 5: Generator set

GB/T 9652.2 Hydraulic turbine control system test

DL/T 583 Technical Specifications of Static Rectification Excitation System for Large and Medium-sized Hydrogenerators

DL/T 724 Technical Regulations for Operation and Maintenance of Battery DC Power Supply Device for Power System

NB/T 35044 Design code for power consumption of hydropower plant

3 Terms and definitions

The following terms and definitions apply to this document.

3.1 Factory electricity working power supply (normal service power supply)

The power supply for the power plant to ensure the normal operation of the main and auxiliary equipment during the production process.

3.2 Factory power backup power (standby service power supply)

After the working power of the plant power is withdrawn, ensure that the main and auxiliary equipment continue to operate normally during the production process of the power plant.

3.3 Black-start power supply

When the working power and standby power of the plant power disappear, other power sources independent of the grid are used to start the unit and its auxiliary equipment.

3.4 Class A black-start mode

Only the electric energy stored in the DC battery and the hydraulic energy stored in the hydraulic system are used to restore the working power of the plant.

3.5 Class B black-start mode

Utilize the electrical energy stored in the black start power supply and the DC battery and the hydraulic energy stored in the hydraulic system to restore the way.

3.6 Black-start of hydropower station

When the hydropower station loses the power supply and standby power for the plant power, the black power is used to restore the power supply for the plant power and the operation of the unit equipment. OK process.

......
This preview omits tables, figures, formulas and parts of the technical clauses. The complete document — 17 pages — is available in the English PDF.

Referenced standards

Similar standards

How to Download GB/T 38334-2019

  1. 1

    Add to cart

    Click "Download PDF" on this page and choose "Buy this standard". You can add more standards before checkout.

  2. 2

    Checkout

    Enter your email and billing details. Payment is processed securely by Stripe (cards or bank transfer). Prefer bank details? Request a quotation (min. order $300).

  3. 3

    Instant delivery (0–9 sec)

    Delivery is automatic: within seconds of payment you'll receive an email with a secure download link. The link stays valid for 72 hours.

  4. 4

    Invoice included

    A tax invoice is attached to the confirmation email. Need a custom invoice? Contact us.

Related Standards

English PDF
17 pages
Instant delivery (0–9 sec)
Invoice included
View Cart

Secure payment via Stripe

Payments accepted

VisaMastercardAmerican ExpressApple PayGoogle PayStripe

GB/T 38334-2019

$295.00