Scope
GB/T 33735-2017 is the English-translated version of 中小学校地震避险指南.
GB/T 33735-2017 is the Chinese guideline on how primary and middle schools avoid earthquake danger. It gives the content, the procedures, the methods and the requirements for three stages: preparation before an earthquake, taking shelter while the ground is shaking, and evacuation once the shaking has stopped.
The clause on preparation asks each school for an earthquake avoidance plan, on its own or inside the emergency plan, and lists what the plan records: the nature of the school, its subordination, the numbers of teachers and pupils, the type of the school buildings, the distribution of load-bearing walls, the geological hazards around the site, the evacuation routes and places, and the risk points.
Other schools may follow it. It cites GB 13495.1, GB 50016 and GB 50099, was issued on 12 May 2017 and has applied since 1 December 2017.
Found what you need?
Document preview — GB/T 33735-2017
National Standard of the People's Republic of China
- ICS
- 91.120.25
- Classification
- P 15
Issued by: State Administration for Market Regulation; Standardization Administration of the PRC
Contents
- Foreword
- Introduction
- 1 Scope
- 2 Normative reference documents
- 3 Terms and definitions
- 4 Earthquake preparedness
Foreword
The standards are drafted in accordance with the rules given in GB/T 1.1-2009.
Introduction
In China's catastrophic earthquake and earthquake, sometimes there are primary and secondary students due to improper hedge caused by casualties, such as the location of the escape is not When, shocked outdoors on the way to be smashed, jumping and other casualties caused.
The purpose of this standard is to provide primary and secondary schools with earthquake relief work basis, to promote the work of earthquake prevention and mitigation in primary and secondary schools Barrier to the rapid and orderly risk hike and post-earthquake evacuation, to maximize the protection of students and staff life safety.
China is a serious earthquake disaster countries, people in the lessons of the earthquake, summed up some effective earthquake hedging methods. Such as Tangshan After the earthquake summed up the "earthquake to avoid the nearest, after the earthquake quickly evacuated" approach, Wenchuan earthquake summed up the "run to run, can not run to hide" approach, a Some strong sense of the earthquake summed up the "can not jump, can not blindly escape" approach. Primary and secondary schools are closely organized personnel-intensive places, small Students have the ability to accept strong, but do not have full capacity. This standard is based on the experience and lessons of historical earthquakes, combined with the school Characteristics of the development.
1 Scope
This standard gives the primary and secondary schools earthquake avoidance preparation, earthquake hedging, post-earthquake evacuation content, procedures, methods and requirements.
This standard applies to primary and secondary school earthquake hedging work, other schools or other disaster hedging can also refer to the use.
2 Normative reference documents
The following documents are indispensable for the application of this document. For dated references, only the dated edition applies to this document. For undated references, the latest edition (including all modifications) applies to this document.
GB 13495.1 Fire safety signs - Part 1: Marking
GB 50016 Code for fire protection of building design
GB 50099 Code for design of primary and secondary schools
3 Terms and definitions
The following terms and definitions apply to this document.
3.1 Earthquake danger avoidance
In order to alleviate the earthquake caused by the building (structure) buildings or other facilities to damage the damage to the people to take the earthquake before the hedge, Emergency measures after evacuation. [GB/T 30353-2013, definition 3.3]
3.2 Earthquake avoidance
Occurrence of the earthquake occurred when the nearest evasive and evacuated behavior. [GB/T 30353-2013, definition 3.1]
3.3 Post - earthquake evacuation
After the end of the earthquake, the organization personnel in an orderly withdrawal from the building (structure) building hedging behavior. [GB/T 30353-2013, definition 3.2]
4 Earthquake preparedness
4.1 Earthquake relief plan
4.1.1 Earthquake hedging plan can be developed separately, or in the earthquake emergency plan, emergency contingency plans to increase the earthquake hedging content. main content include.
a) school basic situation. Including the nature of the school, subordinate relationship, teacher, the number of students, school building (structure) building type, Quasi-load-bearing wall distribution, surrounding geological hazards, evacuation routes, evacuation sites, possible risk situations and risks Point
......
This preview omits tables, figures, formulas and parts of the technical clauses. The complete document — 15 pages — is available in the English PDF.
Referenced standards
Similar standards
How to Download GB/T 33735-2017
- 1
Add to cart
Click "Download PDF" on this page and choose "Buy this standard". You can add more standards before checkout.
- 2
Checkout
Enter your email and billing details. Payment is processed securely by Stripe (cards or bank transfer). Prefer bank details? Request a quotation (min. order $300).
- 3
Instant delivery (0–9 sec)
Delivery is automatic: within seconds of payment you'll receive an email with a secure download link. The link stays valid for 72 hours.
- 4
Invoice included
A tax invoice is attached to the confirmation email. Need a custom invoice? Contact us.
Related Standards
GB 13495.1-2015 — Fire safety signs - Part 1: Signs
GB 50016-2014 — Code for Fire Protection Design of Buildings (2018 Edition)
GB 50016-2018 — [2018 Edition of GB 50016-2014] Code for Fire Protection Design of Buildings [Code of Design on Building Fire Protection and Prevention]
Secure payment via Stripe
Payments accepted
GB/T 33735-2017
$145.00