GB/T 42318-2023Guide for environmental impact assessment of electrochemical energy storage station (English PDF)

电化学储能电站环境影响评价导则

Open the GB/T 42318-2023 preview as PDF

Preview — first pages of GB/T 42318-2023 (full document: 22 pages)

This is a limited preview

Buy now to download the full PDF (22 pages)

Issued by

SAMR; SAC

Level / Type

National · Recommended

Issue date

March 17, 2023

Implementation date

October 1, 2023

Scope

GB/T 42318-2023 is the English-translated version of 电化学储能电站环境影响评价导则.

GB/T 42318-2023 covers how the environmental impact of an electrochemical energy storage station is assessed and written up - the general requirements for the assessment, the overview of the station itself with its name, the nature and location of the works, its scale, its site and the area and type of that site, the survey and assessment of the environment as it already stands, the prediction and assessment of the impacts the station will add, the protection measures, the management and monitoring plan, and the conclusion the report has to reach. The status survey is scoped so that it reflects the environmental background of the area and the problems already present in it, which is what allows the contribution of the station to be separated from what it inherits. Protection measures are set against the object, scope and degree of each adverse impact and run from prevention through reduction to restoration, rather than being listed in the abstract. Appendix A sets out the assessment process as a flow. Storage stations are built where the load is, which usually means close to people, and this report is the document a reviewing authority approves or refuses the site on. Written for developers, environmental assessment institutes and reviewing authorities.

Document preview — GB/T 42318-2023

National Standard of the People's Republic of China

ICS
27.180
Classification
F 19

Issued by: State Administration for Market Regulation; Standardization Administration of the PRC

Contents

  • Foreword3
  • 1 Scope4
  • 2 Normative references4
  • 3 Terms and definitions5
  • 4 General requirements5
  • 5 Overview of the power station6
  • 6 Status survey and assessment7
  • 7 Impact prediction and assessment11
  • 8 Protection measures15
  • 9 Management and monitoring plan17
  • 10 Assessment conclusion17
  • Appendix A (Informative) Environmental impact assessment process of electrochemical energy storage station19
  • References22

Foreword

This document was issued on 17 March 2023 by the State Administration for Market Regulation; Standardization Administration of the PRC and takes effect on 1 October 2023.

It is a GB/T standard: recommended rather than compulsory, but it is the text a Chinese reviewer applies when assessing a submission.

1 Scope

GB/T 42318-2023 covers how the environmental impact of an electrochemical energy storage station is assessed and written up - the general requirements for the assessment, the overview of the station itself with its name, the nature and location of the works, its scale, its site and the area and type of that site, the survey and assessment of the environment as it already stands, the prediction and assessment of the impacts the station will add, the protection measures, the management and monitoring plan, and the conclusion the report has to reach. The status survey is scoped so that it reflects the environmental background of the area and the problems already present in it, which is what allows the contribution of the station to be separated from what it inherits. Protection measures are set against the object, scope and degree of each adverse impact and run from prevention through reduction to restoration, rather than being listed in the abstract. Appendix A sets out the assessment process as a flow. Storage stations are built where the load is, which usually means close to people, and this report is the document a reviewing authority approves or refuses the site on. Written for developers, environmental assessment institutes and reviewing authorities.

This document specifies the general situation, status survey and assessment, impact

prediction and assessment, protection measures, management and monitoring plans,

and assessment conclusions of electrochemical energy storage station.

This document is applicable to the environmental impact assessment of electrochemical

energy storage stations using lithium-ion cells, flow cells, lead-acid (carbon) cells,

sodium-ion cells, and water-electrolysis-produced hydrogen/fuel cells as energy storage

carriers.

2 Normative references

The following documents, in whole or in part, are normatively referenced in this

document and are indispensable to its application. For dated references, only the version

corresponding to that date is applicable to this document; for undated references, the

latest version (including all amendments) is applicable to this document.

GB 3096, Environmental quality standard for noise

GB 8702, Controlling limits for electromagnetic environment

GB 12348, Emission standard for industrial enterprises noise at boundary

GB 15603, Rule for storage of chemical dangers

GB 17914, Specifications for storage and preservation of combustible and explosive

goods

GB 17915, Specifications for storage and preservation of corrosive goods

DL/T 2528, General terminology of electrical energy storage

HJ 2.1, Technical guideline for environmental impact assessment of construction

project - General programme

HJ 2.2, Guidelines for environmental impact assessment - Atmospheric environment

HJ 2.3, Technical guidelines for environmental impact assessment - Surface water

environment

4.3 The environmental impact factors involved in the electrochemical energy storage

station include the atmosphere, surface water, groundwater, soil, sound,

electromagnetic and ecological environment. The identification of environmental

impact factors shall clarify the relationship between the various behaviors of the

electrochemical energy storage station during the construction period, operation period

and post-service period AND the possible environmental factors that may be affected,

the nature of influence, the scope of influence, the degree of influence, etc. Analyze the

pollution impact and ecological impact that the electrochemical energy storage station

may have on various environmental elements, including favorable and unfavorable

impacts, long-term and short-term impacts, reversible and irreversible impacts, direct

and indirect impacts, cumulative and non-cumulative impacts, etc.

4.4 Assessment factors shall be screened and determined based on the identification of

environmental impact factors and combined with regional environmental function

requirements.

4.5 When the electrochemical energy storage station is located in an environmentally

sensitive area specified in the Classification Management List for Environmental

Impact Assessment of Construction Project, it shall explain the reason for building in

the sensitive area, the impact of the battery on the environment, and carry out ecological

planning compliance, environmental rationality, and project feasibility analysis.

4.6 The assessment grade and assessment range of atmospheric environment, surface

water environment, groundwater environment, soil environment, noise environment,

electromagnetic environment and ecological environment shall comply with the

regulations of HJ 2.1, HJ 2.2, HJ 2.3, HJ 610, HJ 964, HJ 2.4, HJ 24 and HJ 19.

4.7 The assessment period includes three periods: construction period, operation period

and post-service period. The assessment level year shall be determined according to the

characteristics of the electrochemical energy storage station and its surrounding

environment, and the recovery of environmental impacts. The status assessment level

year can be 1 to 2 years before the start of construction; the prediction and assessment

level year of the construction period can be the first year of the construction period; the

predication and assessment level year of the operation period can be 1 to 2 years after

operation; the prediction and assessment level year of the post-service period can be

one year after the expiration of the service period.

Remaining clauses in the full document

  • 3 Terms and definitions
  • 4 General requirements
  • 5 Overview of the power station
  • 6 Status survey and assessment
  • 7 Impact prediction and assessment
  • 8 Protection measures
  • 9 Management and monitoring plan
  • 10 Assessment conclusion

......
This preview omits tables, figures, formulas and parts of the technical clauses. The complete document — 22 pages — is available in the English PDF.

Referenced standards

Normative references

GB 3096, Environmental quality standard for noise · GB 8702, Controlling limits for electromagnetic environment · GB 12348, Emission standard for industrial enterprises noise at boundary · HJ 2.1, Technical guideline for environmental impact assessment of construction · HJ 2.2, Guidelines for environmental impact assessment - Atmospheric environment · HJ 2.3, Technical guidelines for environmental impact assessment - Surface water

Similar standards

GB 38031-2025|GB 3096|GB 8702|GB 12348|GB 15603|GB 17914|GB 17915|GB 12348

How to Buy GB/T 42318-2023

  1. 1Add to cart. Click the "Buy GB/T 42318-2023" button on this page. You can add more standards before checkout.
  2. 2Checkout. Enter your email and billing details. Payment is processed securely by Stripe (cards, Apple Pay, Google Pay supported).
  3. 3Instant delivery (0–9 sec). Delivery is automatic: within seconds of payment you'll receive an email with a secure download link. The link stays valid for 72 hours.
  4. 4Invoice included. A tax invoice is attached to the confirmation email. Need a custom invoice? Contact us.

Related Standards

English PDF
22 pages
Instant delivery (0–9 sec)
Invoice included
View Cart

Secure payment via Stripe

Payments accepted

VisaMastercardAmerican ExpressApple PayGoogle PayStripe

GB/T 42318-2023

$245.00

$210.00for partners