Scope
GB/T 25737-2025 is the English-translated version of 1000kV变电站监控系统验收规范.
GB/T 25737-2025 is the Chinese national standard covering signing off the monitoring system of an ultra-high-voltage substation — the conditions that must hold before acceptance can start, the factory acceptance of function, performance and stability, the on-site tests on the secondary circuits and the joint commissioning with the dispatch centre, the rectification of what is found, the acceptance report and the filing that later operators rely on, and the responsibilities of each unit involved. It replaces GB/T 25737-2010, under the China Electricity Council. In force from 1 November 2025. Issued on 1 August 2025, it has been in force since 1 November 2025, replacing GB/T 25737-2010.
Document preview — GB/T 25737-2025
National Standard of the People's Republic of China
- ICS
- 27.100
- Classification
- F 23
- Replacing
- GB/T 25737-2010
Issued by: State Administration for Market Regulation; Standardization Administration of the PRC
Contents
- PrefaceIII
- 1 Scope1
- 2 Normative references1
- 3 Terms and Definitions1
- 4 Acceptance Conditions1
- 4.1 Basic conditions1
- 4.2 Factory Acceptance Conditions2
- 4.3 On-site acceptance conditions2
- 5 Acceptance Process2
- 6 Acceptance Content2
- 6.1 Basic Content2
- 6.2 Factory Acceptance3
- 6.3 On-site acceptance3
- 7 Acceptance and rectification3
- 7.1 Factory Acceptance and Rectification3
- 7.2 On-site acceptance and rectification3
- 8 Acceptance Results3
- 8.1 Acceptance3
- 8.2 Acceptance Report4
- 8.3 Acceptance Materials Filing4
- Appendix A (Informative) Responsibilities of relevant acceptance units5
- A.1 Responsibilities of the project construction unit5
- A.2 Responsibilities of the acceptance working group5
- A.3 Responsibilities of the dispatching organization5
- A.4 Responsibilities of Equipment Operation and Maintenance Unit5
- A.5 Responsibilities of Technical Support Units5
- A.6 Responsibilities of the installation and commissioning unit6
- A.7 Responsibilities of the Design Unit6
- A.8 Responsibilities of System Integrators and Equipment Suppliers6
- Appendix B (Normative) Acceptance Outline7
- B.1 Preparation Basis7
- B.2 Acceptance Outline Contents7
- Appendix C (Normative) Factory Acceptance Test Contents8
- C.1 System Function Test8
- C.2 System Performance Test10
- C.3 System Stability Test11
- C.4 System Optional Function Test11
- Appendix D (Normative) Site Acceptance Test Contents12
- D.1 Secondary circuit acceptance test12
- D.2 Monitoring system test12
- D.3 Joint commissioning and testing of main plant and station12
- D.4 Other tests13
Foreword
This document is in accordance with the provisions of GB/T 1.1-2020 "Guidelines for standardization work Part 1: Structure and drafting rules for standardization documents" Drafting.
This document replaces GB/T 25737-2010 "1000kV substation monitoring system acceptance specification" and is consistent with GB/T 25737-2010.
In addition to structural adjustments and editorial changes, the main technical changes are as follows.
— Added acceptance conditions such as product inspection, safety and reliability, and acceptance environment (see Chapter 4);
— Added content related to the acceptance process and clarified the acceptance organization process (see Chapter 5);
— Added a chapter on basic acceptance content, refined the common parts of factory acceptance and on-site acceptance, and added new protocol documents, configuration files, etc.
Review requirements and system and equipment information consistency verification requirements (see 6.1);
— Added content related to acceptance and rectification, and clarified the requirements for rectification of problems during the acceptance period (see Chapter 7);
— Added content related to acceptance results, clarified acceptance conditions, acceptance reports and acceptance material filing requirements (see Chapter 8);
— Changed the responsibilities of each unit in the acceptance working group (see Appendix A, Chapter 4 of the 2010 edition);
— Added acceptance test items for functions such as sequential control and intelligent alarm (see Appendix C);
— Added the main plant station joint commissioning test content (see Appendix D).
Please note that some of the contents of this document may involve patents. The issuing organization of this document does not assume the responsibility for identifying patents.
This document was proposed by the China Electricity Council.
This document is under the jurisdiction of the National Technical Committee for Ultra-High Voltage AC Transmission Standardization (SAC/TC569).
This document was drafted by: China Electric Power Research Institute Co., Ltd., State Grid Corporation of China, China Southern Power Grid Co., Ltd., State Grid Tianjin Electric Power Company, State Grid Shanghai Electric Power Company, China Southern Power Grid Co., Ltd. Ultra-high Voltage Transmission Company, State Grid Hunan Province Power Co., Ltd., Guangxi Power Grid Co., Ltd. Electric Power Research Institute, State Grid Liaoning Electric Power Co., Ltd., State Grid Chongqing Electric Power Co., Ltd.
Electric Power Research Institute of State Grid Corporation of China, Electric Power Research Institute of Guizhou Power Grid Co., Ltd., Electric Power Research Institute of State Grid Hebei Electric Power Company, North China Electric Power University, State Grid Shandong Electric Power Company, State Grid Corporation of China Northeast Branch, and State Grid Corporation of China East China Branch.
The main drafters of this document are: Li Ang, Chang Naichao, Li Jin, Xie Xin, Chen Jian, Zhang Jinhu, Chen Hongfu, Zhang Kefeng, Li Yalei, Li Long, Zhou Ke, Wang Shunjiang, Zeng Zhiqiang, Li Jinsong, Xu Changbao, Gao Jun, Lv Fangcheng, Liu Yong, Zhao Na, Peng Fei, Li Wenzhuo, and Zhang Liang.
The previous versions of this document and the documents it replaces are as follows.
— First published in 2010 as GB/T 25737-2010;
— This is the first revision.
1 Scope
This document specifies the acceptance conditions, acceptance process, acceptance content, acceptance rectification and acceptance results of the 1000kV substation monitoring system. Require.
This document is applicable to the acceptance of 1000kV substation monitoring systems. It can be used as a reference for the acceptance of substation monitoring systems at other voltage levels.
2 Normative references
GB/T 24833
3 Terms and Definitions
The terms and definitions defined in GB/T 24833 and the following apply to this document.
3.1 and performance testing
According to the contract and technical agreement requirements, before leaving the factory, the system integrator or equipment manufacturer shall conduct functional inspection according to the factory acceptance outline.
3.2 Site acceptance test site acceptance test; SAT
According to the contract and technical agreement, after the system or equipment arrives at the site and completes installation and commissioning, before it is put into operation, the site acceptance inspection Functional and performance testing is carried out.
4 Acceptance conditions
4.1 Basic conditions
The acceptance of the 1000kV substation monitoring system includes factory acceptance and on-site acceptance, and should meet the following conditions.
a) The unit responsible for the construction of the project shall organize and establish an acceptance working group. The responsibilities of the relevant units are shown in Appendix A;
b) The acceptance outline is completed and prepared in accordance with the requirements of Appendix B;
c) The project contract documents, design liaison meeting documents and other project-related agreements are complete;
d) The design drawings and configuration files required for the project have been completed and approved;
e) The substation monitoring system and related access equipment have obtained valid and qualified certificates issued by a testing agency with national or industry testing qualifications. Third-party test report;
f) The substation monitoring system and access equipment meet the safety and reliability requirements in the bidding documents;
g) The acceptance tools such as instruments and meters are fully equipped and have obtained the verification/calibration certificate issued by the national legal metrology department or other legally authorized units.
Approval certificate, and within the validity period;
......
This preview omits tables, figures, formulas and parts of the technical clauses. The complete document — 15 pages — is available in the English PDF.
Referenced standards
Normative references
Editions of GB/T 25737
| Edition | Title | Revision | Status |
|---|---|---|---|
| GB/T 25737-2025 | Acceptance specification for 1000kV substation monitoring system | current edition | Current |
| GB/T 25737-2010 | Acceptance norms for 1000kV substation monitoring system | previous edition | In force |
This page sells the current edition, GB/T 25737-2025. Earlier editions are listed for reference only.
How to Buy GB/T 25737-2025
- 1Add to cart. Click the "Buy GB/T 25737-2025" button on this page. You can add more standards before checkout.
- 2Checkout. Enter your email and billing details. Payment is processed securely by Stripe (cards, Apple Pay, Google Pay supported).
- 3Instant delivery (0–9 sec). Delivery is automatic: within seconds of payment you'll receive an email with a secure download link. The link stays valid for 72 hours.
- 4Invoice included. A tax invoice is attached to the confirmation email. Need a custom invoice? Contact us.
Related Standards
GB/T 24833-2009 — Technical specification for 1000kV substation automation system
GB/T 47310-2026 — Determination of total silicon, aluminium, iron, potassium, sodium, calcium, magnesium, manganese, phosphorus, titanium and sulfur in soil - Monochromatic excitation energy dispersive X-ray fluorescence spectrometry
GB/T 47321-2026 — Specification for the warning data exchange of the national emergency early warning dissemination system
Secure payment via Stripe
Payments accepted
GB/T 25737-2025
$245.00