Valid

GB/T 45964-2025Technical specification for disintegrating of molten steel slag by self-generating steam (English PDF)

熔融钢渣热闷技术规范

Open the GB/T 45964-2025 preview as PDF

Preview — first pages of GB/T 45964-2025 (full document: 15 pages)

This is a limited preview

Buy now to download the full PDF (15 pages)

Issued by

SAMR; SAC

Level / Type

National · Recommended

Issue date

August 1, 2025

Implementation date

February 1, 2026

Scope

GB/T 45964-2025 is the English-translated version of 熔融钢渣热闷技术规范.

GB/T 45964-2025 is the Chinese national standard covering steam raised by the slag's own heat to break it down — the pressurised and atmospheric tank routes and the pool route for converter and electric arc furnace slag, the process flow, the equipment and the automation, the process water, the dust removal and the particulate emission, and the digestion of free calcium oxide and free magnesium oxide that would otherwise swell later in a road base or a cement. First edition, under the China Iron and Steel Association. In force from 1 February 2026. Issued on 1 August 2025, it has been in force since 1 February 2026.

Document preview — GB/T 45964-2025

National Standard of the People's Republic of China

ICS
77.140.99
Classification
H 34

Issued by: State Administration for Market Regulation; Standardization Administration of the PRC

Contents

  • Foreword
  • 1 Scope
  • 2 Normative references
  • 3 Terms and Definitions
  • 3.1 A method for rapidly digesting magnesium oxide and pulverizing steel slag
  • 3.2 A method for rapidly digesting and pulverizing steel slag
  • 4 Basic Requirements

Foreword

This document is in accordance with the provisions of GB/T 1.1-2020 "Guidelines for standardization work Part 1: Structure and drafting rules for standardization documents" Drafting.

Some of the contents of this document may involve patents. The issuing organization of this document shall not be responsible for identifying patents.

This document was proposed by the China Iron and Steel Association.

This document is under the jurisdiction of the National Technical Committee on Steel Standardization (SAC/TC183).

This document was drafted by: China Metallurgical Construction Research Institute Co., Ltd., Wuxi Juli Heavy Industry Co., Ltd., Jiangsu Binxin Iron and Steel Group Co., Ltd., MCC Energy Conservation and Environmental Protection Co., Ltd., Shougang Group Qian'an Iron and Steel Company, Metallurgical Industry Information Standards Research Institute, Beijing Science and Technology University of Science and Technology, Shiheng Special Steel Group Co., Ltd., Yancheng Institute of Technology, Hangzhou Xiruidi Technology Co., Ltd., Cangzhou China Railway Equipment Manufacturing Materials Co., Ltd.

Co., Ltd., Anhui University of Technology, and Hangzhou Ruikun Information Technology Co., Ltd.

The main drafters of this document are: Du Hongtao, Lu Wen, Zhang Liangliang, Wang Fengliang, Qiu Jinhui, Peng D, Wang Yanbing, Lin Tao, Zhu Liang, Hao Yidang, Zhao Hongzhu, Ma Hongzhi, Qi Baoxiang, Zhang Fei, Wu Jianzhong, Yang Junfeng, Wang Jiangwei, Zhang Ruopeng, Zhang Lianhang, Yu Yang, Wu Zhi, Yin Zhifeng, Zhu Huajun, Yan Chaogang, Wang Yupeng, Li Canhua, Pan Na, Xi Yujie, Chen Jian, Wang Xiaojie, Yu Jingyao, Ding Zhongliang, Zhang Yuanchun, Zhang Xingzhou, Cheng Weihua, Du Gang, Zhang Ruichao and Wang Kun.

Technical specification for hot stuffing of molten steel slag

1 Scope

This document specifies the basic requirements, process flow, hot stuffing of molten steel slag tanks with pressure, hot stuffing of molten steel slag tanks with normal pressure, hot stuffing of molten steel slag tanks, hot stuffing of molten steel slag tanks with high pressure...

Pressure heating, molten slag pool heating, tank heating, pool heating, equipment requirements, automation requirements, dust removal design and particulate matter removal Release requirements and water requirements for slag treatment.

This document is applicable to the tank-type pressurized hot stuffing treatment, tank-type atmospheric pressure hot stuffing treatment and pool-type hot stuffing treatment of converter and electric arc furnace steel slag.

2 Normative references

GB/T 3766

GB/T 20491

GB/T 25824

GB 50010

3 Terms and Definitions

The terms and definitions defined in YB/T 804 and the following apply to this document.

3.1 A method for rapidly digesting magnesium oxide and pulverizing steel slag

The hot slag is put into the pressure hot stuffing device, and water is sprayed to generate pressurized steam above 100°C, which makes the free calcium oxide and free oxygen in the slag

3.2 A method for rapidly digesting and pulverizing steel slag

The hot slag is placed in a normal pressure hot stuffing device, and water is sprayed to generate 100°C normal pressure steam, which dissociates the free calcium oxide and free magnesium oxide in the slag.

4 Basic Requirements

4.1 The steel slag hot stuffing treatment system should be designed, constructed and put into operation at the same time as the main steelmaking project.

4.2 The dust removal and other pollution prevention facilities supporting the steel slag hot stuffing treatment line should be designed and constructed at the same time as the main steel slag hot stuffing treatment project.

Put into use at the same time.

......
This preview omits tables, figures, formulas and parts of the technical clauses. The complete document — 15 pages — is available in the English PDF.

Referenced standards

Editions of GB/T 45964

EditionTitleRevisionStatus
GB/T 45964-2025Technical specification for disintegrating of molten steel slag by self-generating steamcurrent editionCurrent

This page sells the current edition, GB/T 45964-2025. Earlier editions are listed for reference only.

How to Buy GB/T 45964-2025

  1. 1Add to cart. Click the "Buy GB/T 45964-2025" button on this page. You can add more standards before checkout.
  2. 2Checkout. Enter your email and billing details. Payment is processed securely by Stripe (cards, Apple Pay, Google Pay supported).
  3. 3Instant delivery (0–9 sec). Delivery is automatic: within seconds of payment you'll receive an email with a secure download link. The link stays valid for 72 hours.
  4. 4Invoice included. A tax invoice is attached to the confirmation email. Need a custom invoice? Contact us.

Related Standards

English PDF
15 pages
Instant delivery (0–9 sec)
Invoice included
View Cart

Secure payment via Stripe

Payments accepted

VisaMastercardAmerican ExpressApple PayGoogle PayStripe

GB/T 45964-2025

$185.00

$155.00for partners