Valid

GB/T 44107-2024Risk management - Large scientific installations - Risk classification and control measures (English PDF)

风险管理 大科学装置风险分类及控制措施

Open the GB/T 44107-2024 preview as PDF

Preview — first pages of GB/T 44107-2024 (full document: 16 pages)

This is a limited preview

Buy now to download the full PDF (16 pages)

Issued by

SAMR; SAC

Level / Type

National · Recommended

Issue date

June 29, 2024

Implementation date

June 29, 2024

Scope

GB/T 44107-2024 is the English-translated version of 风险管理 大科学装置风险分类及控制措施.

GB/T 44107-2024 establishes the principles by which the risks of a large scientific installation are classified, and lays down the classification itself and the control measures that go with it. It applies to risk management activities across the whole life cycle of such an installation, and it cites no normative references. Risks are sorted into five families: core value risk, covering scientific value and technical development; social risk, covering the international political, policy and economic environment and social stability; organization management risk, covering project management, cooperation management, suppliers and the supply chain, exchange, data management, project baselines and intellectual property; technology risk, covering the natural environment, requirements and scope, design, manufacturing and machining, construction, interfaces, integration and assembly, commissioning and operation, and safety and quality; and funding risk. For each of these, Clause 5 lists the contributing factors in an open-ended form. Clause 6 then sets out control measures stage by stage, following the installation from preliminary research through scheme design and manufacturing and construction to operation and maintenance, and cross-referring the measures of one stage to another where they repeat.

Document preview — GB/T 44107-2024

National Standard of the People's Republic of China

ICS
03.120.01
Classification
A 02

Issued by: State Administration for Market Regulation; Standardization Administration of the PRC

Contents

  • 1 Scope1
  • 2 Normative references1
  • 3 Terms and definitions1
  • 4 Classification principles2
  • 5 Risk classification2
  • 6 Risk control measures7
  • Bibliography16

3 Terms and definitions

3.1 Large scientific installation: a large facility built through relatively large investment and engineering work which, after construction, achieves important scientific and technological goals through long-term stable operation and continuing scientific and technical activity.

3.2 and 3.3 Risk is the adverse effect of uncertainty on the whole life cycle of a large scientific installation, and risk management is, in respect of the risks of a large scientific installation, the coordinated activities to direct and control an organization; both are taken from GB/T 23694-2013, modified.

3.4 to 3.8 Core value risk is the situation in which the project result departs from what was expected because of scientific value, technical development and similar factors during construction; social risk is the same situation caused by political factors, policy change, economic conditions and outside comment; organization management risk is that caused by project management, cooperation management, international exchange and supplier management; technology risk is that caused by technical factors; and funding risk is that caused by shortcomings in financing planning, use of funds, securing of funds and analysis of investment return.

4 Classification principles

4.1 Scientific soundness: the classification takes the features of the most basic large scientific installations as the basis for risk analysis, in the light of the significance of the different installations and the characteristics of their fields, so that the classification is complete and soundly reasoned.

4.2 Practicality: the classification is practical and can support the responsible units in design, construction, operation and maintenance. 4.3 Compatibility: the classification stays consistent with existing risk classification principles and methods and takes account of changes in technology and business.

5 Risk classification

5.1 Core value risk covers scientific value risk and technical development risk. The factors that give rise to scientific value risk include a scientific goal that is not forward-looking enough, insufficient urgency in the challenge the project addresses, and the absence of an assessment of the scientific and technological results and of the economic and social benefits. Those behind technical development risk include incomplete or unreliable basic data, failure to track technical developments and changes in scientific value so that the advancement of the project suffers, the possibility that the technology under development does not reach the expected effect, the possibility that the technology ceases to be supported, and incompatibility across systems in hardware or software.

5.2 Social risk covers international political environment risk, policy environment risk, economic environment risk and social stability risk. The factors listed include changing international relations, local wars and unrest, interest rate movements, fluctuation of the international economic environment, trade policy change and inflation; adjustments of development strategy by governments at all levels, changes in laws and regulations such as the tax system, and the making and revision of mandatory standards such as pollutant emission limits in environmental standards; domestic economic factors such as the level and stability of economic development, the market and industrial environment and the uncertainty of the raw material market, which can raise the price of components, raw materials, test equipment and measuring instruments, together with foreign trade, foreign investment and exchange rate factors; and failure to identify the needs and expectations of the internal and external context and of interested parties, unclear effectiveness of education and popularization of scientific knowledge, the effect on residents of noise and air pollution during construction and operation that does not meet national standards, latent threats to local public order, and public opinion risk where explanation and guidance are inadequate.

5.3 Organization management risk covers project management risk, cooperation management risk, supplier and supply chain capability, exchange risk, data management risk, project baseline risk and intellectual property risk. The factors listed include a project leader whose decision-making level is not high enough and an organization whose management capability is insufficient; the absence of an experienced professional management team able to meet the scientific, technical and performance goals of each life cycle stage; failure to define the roles and responsibilities of partners at the different stages, failure to state the responsibilities of partners for delivered and supplied items, failure to allow for the evolution of the partnership and the absence of a sound admission system, and different information standards between partners and between the design and construction units; insufficient market research with single-source procurement or poor supplier selection, a supply chain without enough depth to secure competition, inability to find qualified suppliers or contractors, insufficient capacity, qualifications, experience or skills in the supply chain, availability of materials and parts, and inadequate human resource reserves; failure to set an international exchange policy early and the effect of a changing political environment on such exchange; the absence of a transparent and open data management policy, failure to use advanced electronic infrastructure services for access, processing and management of data and for remote participation, and unstable or unsuitable electronic systems and permission allocation; insufficient consideration in the schedule and cost estimates and inadequate resource planning; and the absence of an intellectual property policy with clear goals, failure to search the literature at the start of the project, failure to protect new technologies and products under development in time, failure to publish and restrict the intellectual property of the parties, the absence of incentives for innovation, technology transfer and intellectual property management, and disregard of the intellectual property evaluation of suppliers and of the products procured from them.

5.4 Technology risk covers natural environment risk, requirement and scope risk, design risk, manufacturing and machining risk, construction risk, interface, integration and assembly risk, commissioning and operation risk, and safety and quality risk. The factors listed include the absence of an environmental assessment and known or latent environmental problems, failure to allow for environmental permits, ecological pollution and degradation, and undefined methods for disposing of scrapped equipment; undefined, incomplete or unclear requirements or functions, inadequate requirement analysis, unstable requirement sources, requirements that are hard to trace and measure, non-compliant or invalid requirements, failure to agree with interested parties on the foreseeable scope, time and cost, failure to assess the gap between requirements and scope, and unreasonable work package breakdown; failure to justify complex design features, too many unproven new technologies, incompatibility between designs, numerous or unclear assumptions, aspects of the design left unresolved because requirements and scope are unclear, inadequate or wrongly applied design criteria, known or latent errors or omissions, uncontrolled change processes and known or latent design integration problems; inadequate design documents for a valid manufacturing plan or control specification, a manufacturing process that cannot produce parts to the design standard, incomplete functional breakdown in the systems engineering, accumulated tolerances that put manufacture and assembly at risk, out-of-tolerance production, possible mechanical failure at the manufacturing stage, poor information transfer between the design, manufacturing and assembly teams, verification testing cut short for budget or schedule reasons, and the possibility that equipment cannot be used; ground conditions on site that differ from what was expected, no simulation or testing of the suitability of the building interfaces, quality change of equipment and parts from transport and storage, interference between the building and the plant installation, unidentified maintenance problems in stored equipment, and site safety systems and site management that do not keep the workers safe; unstable or unfrozen interfaces, possible insufficient system integration between buildings and systems and between systems, interference between the working areas of the parties, an insufficiently defined assembly plan, difficulty in running a multi-shift assembly model, limited space inside the building, limited function of tooling and equipment, possible rework from incompatibility of components or systems, and assembly tolerances already beyond what is allowed; possible failure of major parts or equipment at the operating stage, unplanned interference where several subcontractors work in the same area, problems from insufficiently defined maintenance procedures, and a shortage of spare parts; and hazardous substances, potential serious pollution, a new design basis that introduces accident risk or unreviewed safety risk, safety grading or systems with safety risk, problems in the running of the quality management system, poor information transfer between the design, manufacturing and assembly teams, change requests carried out without careful analysis, verification testing cut short for budget or schedule reasons, and out-of-tolerance production.

5.5 Funding risk. The factors listed are the absence of a balanced ratio between the cash and in-kind contributions of the partners, the absence of sound guidance for valuing liabilities or real property, the absence of a reasonable plan for using funds in step with the progress of the project, the effect of changing equipment reliability and depreciation on maintenance costs, changes in the financing environment, diversified funding sources calling for a sound plan for securing the money, an over-optimistic investment return plan with a weak demonstration effect, and, where additional investment is needed later in the project or the budget falls short, the capacity to secure funds, the reasonableness of their allocation and delay in their arrival.

6 Risk control measures

6.1 Before a risk event occurs, the aim is to choose economical, reasonable and effective methods that reduce or avoid it and bring its likelihood and consequences down as far as possible; after one occurs, the parties work together, apply the contingency plan and the measures at once so as to limit casualties and economic loss and the effects on the surrounding environment, on reputation and image and on the political situation, and remove the latent hazard.

6.2 At the preliminary research stage the core value measures are to set up a science and technology committee and hold a project justification, covering feasibility and alignment with international goals and strategy, the urgency of the practical need, the opportunity the project gives national science and engineering for frontier research, the transferability of the technology adopted and the high priority of the field; to win broad support from the research and education community; and to build a relatively broad user base able to meet the research and education goals and the needs of the stated number of users. The social risk measures include investigating the credit and business standing of the parties, building up reserve suppliers for core components, parts, raw materials, test equipment and measuring instruments, following the foreign exchange policy of the host country, signing memoranda of understanding with partners and, where necessary, carrying out a political security analysis; designing according to laws, regulations and standards and tracking their change; and identifying and classifying the customer groups and potential interested parties, analysing users, carrying out a social stability assessment as part of the feasibility study report, assessing public opinion risk in key areas and preparing responses, and assessing technical feasibility, cost, benefit and risk so that the concept design, cost, schedule and performance goals are consistent with the context and the concerns of interested parties. The organization management measures are to discuss the value of the project and the potential cost allocation with the prospective undertaking unit and external partners, to sign memoranda of understanding fixing rights and responsibilities in funding, management and supervision, to negotiate the content and mechanism of international cooperation with the responsible body and to secure cooperation through international organizations and programmes, and to determine the schedule and cost baselines and examine the cost, schedule and benefit of alternative projects. The technology measure is a siting justification covering environmental, ecological, geological, disaster and social assessment, construction standards and the cost of meeting environmental standards; and the funding measures are annual fund allocation drafts and cash flow analyses, early discussion of cost allocation and planning for a shortfall through contingency reserves, deficit sharing and other investment channels.

6.3 At the scheme design stage the core value measures cover technical development risk: the science and technology committee reviews and approves the technical scheme according to the project plan, the scientific, technical and performance goals are assessed and updated externally at intervals, a scientific evaluation method is used throughout the life cycle with the quality of research output, the vigour of the research environment and scientific influence as indicators, and an external team of domestic and foreign experts audits the project at its different stages. The social risk measures follow those of the preliminary research stage, with the addition of contingency cost and contingency schedule in the project budget and plan, further reserve suppliers, education and science popularization programmes with an assessment of their effectiveness, active communication management towards end customers and important interested parties with stable feedback and recommendation channels, and updating and assessment of the requirement list as customers and their needs change. The organization management measures include setting up a suitable management body and an experienced top management team and drawing on the practices and principles of other scientific installations worldwide.

6.4 The manufacturing and construction stage repeats or refers back to the measures of the earlier stages for social, organization management, technology and funding risks, adding measures for policy, economic environment and social stability risk, for project management, cooperation management, supplier, exchange, data management, project baseline and intellectual property risk, and for construction risk.

6.5 At the operation and maintenance stage the technical development measures are to draw up an operation and maintenance plan reviewed and approved by the science and technology committee, to review the scientific and technological needs of the project at intervals with external assessment and updating of the goals, to have an external team of domestic and foreign experts audit the different stages, to apply a scientific evaluation method throughout the life cycle, and to set assessment indicators for the installation in operation covering the make-up of highly qualified staff, the profile of the facility, the operating and maintenance cost, and the lists of technologies, services, users, research results and teaching activities. The organization management measures add operating assessment rules setting targets for the total effective service hours in the year, the effective hours served to third parties, the number of users and the number of papers published, publication of the third-party application procedure and guide on an open platform, and user agreements that lower the barrier to enterprise cooperation, make up the start-up funding and strengthen the transfer of intellectual property. The technology measures are an operation and maintenance plan drawn up from the reliability design requirements and supervised in execution, contingency funding and schedule plans for the operating period, training on the plan and the skills, and external service and user agreements under which the parties take part in operation and maintenance. The funding measures add close review of the extra money arising from installation upgrades driven by new scientific needs, close supervision of the funds used for maintenance, operation, research and education, including training of individual users on special systems and the funds for retiring or transferring unusable equipment, and external service agreements that add funding channels.

......
This preview omits tables, figures, formulas and parts of the technical clauses. The complete document — 16 pages — is available in the English PDF.

How to Buy GB/T 44107-2024

  1. 1Add to cart. Click the "Buy GB/T 44107-2024" button on this page. You can add more standards before checkout.
  2. 2Checkout. Enter your email and billing details. Payment is processed securely by Stripe (cards, Apple Pay, Google Pay supported).
  3. 3Instant delivery (0–9 sec). Delivery is automatic: within seconds of payment you'll receive an email with a secure download link. The link stays valid for 72 hours.
  4. 4Invoice included. A tax invoice is attached to the confirmation email. Need a custom invoice? Contact us.

Related Standards

English PDF
16 pages
Instant delivery (0–9 sec)
Invoice included
View Cart

Secure payment via Stripe

Payments accepted

VisaMastercardAmerican ExpressApple PayGoogle PayStripe

GB/T 44107-2024

$305.00

$260.00for partners