GB/T 25928-2010Automation systems in the process industry -- Factory acceptance test (FAT), site acceptance test (SAT), and site integration test (SIT) (English PDF)
过程工业自动化系统出厂验收测试(FAT)、现场验收测试(SAT)、现场综合测试(SIT)规范
This is a limited preview
Buy now to download the full PDF (30 pages)
Need quotation for your management?
Get a formal quotation for GB/T 25928-2010 in 30 minutes.
Issued by
Standardization Administration of China
Level / Type
National · Recommended
Issue date
January 14, 2011
Implementation date
May 1, 2011
Scope
GB/T 25928-2010 is the English-translated version of 过程工业自动化系统出厂验收测试(FAT)、现场验收测试(SAT)、现场综合测试(SIT)规范.
GB/T 25928-2010 — This standard defines the factory acceptance test (FAT), site acceptance test (SAT) and site integration testing (SIT) procedures and specifications.
These tests are fully automated control system in order to prove compliance with standards. Systems engineering and production activities before the test is not within the scope of this standard involved.
The content of this standard can be used as guidance in practical work for a variety of practical requirements of process, plant and equipment. Figure 1 depicts A typical sequence of events and activities throughout, Figures 2 and 3 shows the relationship between the various stages.
FAT prerequisite. --- Complete software development; --- To complete the system connection; --- Complete Supplier internal testing. SAT prerequisite. --- System has been delivered to the Site; --- Installed correctly; --- System startup.
SIT prerequisite. Room --- system is properly connected; --- To complete the SAT. Note. In fact, during the construction phase, once the basic components required to complete the installation and start the loop test.
Project nodes corresponding to the FAT 1, SAT and SIT typical sequence of events schematic Figure 2 DCS subsystem SAT and SIT phase and phase relationship between the schematic
Found what you need?
Document preview — GB/T 25928-2010
National Standard of the People's Republic of China
- ICS
- 25.040.40
- Classification
- N 10
Issued by: Standardization Administration of China
Contents
- Preface
- Introduction
- 1 Scope
- 2 Terms and definitions
- 3 Acronyms
- We must be prepared prior to the implementation work FAT 4
- 4.1 File owner/general contractor usually prepared
- File 4.2 Suppliers usually prepare
- 5 Factory Acceptance Test FAT
- 5.1 General
- 5.2 FAT test schedule
- 5.3 Test procedure
- 5.4 FAT's review
- 5.5 FAT file (see Appendix A)
- 6 Site Acceptance Test SAT
- 6.1 General
- 6.2 SAT test schedule
- Comprehensive field testing SIT 8
- 7.1 General
- 7.2 SIT test schedule
- Appendix A (informative) Factory Acceptance Test (FAT) Test Table
- Annex B (informative) Site Acceptance Test (SAT) Test Table
- Annex C (informative) Comprehensive field testing (SIT) Checklists
- Appendix D (Informative Appendix) FAT 24 certificate
- Appendix E (Informative Appendix) SAT 25 certificate
- Appendix F (Informative Appendix) SIT certificate
- Annex G (informative) automation systems acceptance certificate
- Appendix H (Informative Appendix) FAT does not meet the entry table
- Annex I (Information Appendix) SAT does not meet the entry table
- Appendix J (Informative Appendix) SIT does not meet the entry table
Foreword
This standard is identical with IEC 62381:2006 "industrial process automation systems --- factory acceptance test (FAT), site acceptance test (SAT), a comprehensive field test (SIT) Specification "(in English).
This standard is equivalent translation IEC 62381:2006, there was no difference in the technical content, for the convenience of users, with the structure of the text on appropriately adjusted, according to GB/T 1.1-2000 "Standardization Guide Part 1. Structure and rules are written standard" and GB/T 20000.2-2001. the relevant provisions of "Standardization Guide Part 2 rules of international standards" were editorial modify.
This standard is mainly made editorial changes as follows.
a) Remove the preface to the international standards;
b) "The document" to the "standard";
c) according to GB/T 1.1-2000 column entry requirements (5.2.5), within the full range of punctuation column item regulate, and Two items listed in section 5.3.2 increases the number for identification.
The Standard Appendix A, Appendix B, Appendix C, Appendix D, Appendix E, Appendix F, Appendix G, Appendix H, Appendix I, Appendix J for information only appendix.
The standard proposed by China Machinery Industry Federation.
This standard by the national industrial process measurement and control Standardization Technical Committee (SAC/TC124) centralized.
Introduction
The current field of process control there is such a phenomenon, the period of the Project were asked to compress getting shorter, while the automatic control system but due to the complexity of the various reasons on the rise, these reasons include the increase relates to the use of communication layers and a variety of new technologies, such as now Field bus system.
Experience shows, owners, general contractors and subcontractors are often used to distinguish their commitment to the standard by consuming huge Gongben discussions and consultations will have Help improve the effectiveness and reduce the time to negotiate consultations, the parties can reach a consensus as soon as possible is responsible for their content.
Appendix to this standard contains the testing process may be used in form. These appendices form using Excel format. The standard purchase
After registration, users can copy these forms according to their needs, but the number should not exceed the number of replication specified.
For the pharmaceutical industry, or other highly specialized industrial applications, some special specifications, instructions and constraints existing file with the current the standard file act together.
Industrial process automation systems Factory Acceptance Test (FAT), site acceptance Test (SAT), a comprehensive field test (SIT) specification
1 Scope
This standard defines the factory acceptance test (FAT), site acceptance test (SAT) and site integration testing (SIT) procedures and specifications.
These tests are fully automated control system in order to prove compliance with standards.
Systems engineering and production activities before the test is not within the scope of this standard involved.
The content of this standard can be used as guidance in practical work for a variety of practical requirements of process, plant and equipment. Figure 1 depicts A typical sequence of events and activities throughout, Figures 2 and 3 shows the relationship between the various stages.
FAT prerequisite.
--- Complete software development;
--- To complete the system connection;
--- Complete Supplier internal testing.
SAT prerequisite.
--- System has been delivered to the Site;
--- Installed correctly;
--- System startup.
SIT prerequisite.
Room --- system is properly connected;
--- To complete the SAT.
Note. In fact, during the construction phase, once the basic components required to complete the installation and start the loop test.
Project nodes corresponding to the FAT 1, SAT and SIT typical sequence of events schematic
Figure 2 DCS subsystem SAT and SIT phase and phase relationship between the schematic
......
This preview omits tables, figures, formulas and parts of the technical clauses. The complete document — 30 pages — is available in the English PDF.
How to Download GB/T 25928-2010
- 1
Add to cart
Click "Download PDF" on this page and choose "Buy this standard". You can add more standards before checkout.
- 2
Checkout
Enter your email and billing details. Payment is processed securely by Stripe (cards or bank transfer). Prefer bank details? Request a quotation (min. order $300).
- 3
Instant delivery (0–9 sec)
Delivery is automatic: within seconds of payment you'll receive an email with a secure download link. The link stays valid for 72 hours.
- 4
Invoice included
A tax invoice is attached to the confirmation email. Need a custom invoice? Contact us.
Related Standards
GB/T 10003-2026 — Biaxially oriented polypropylene (BOPP) film
GB/T 10004-2026 — Plastic/Plastic laminated films and pouches for packaging
GB/T 10007-2026 — Rigid cellular plastics - Determination of shear properties
Secure payment via Stripe
Payments accepted
GB/T 25928-2010
$435.00