NB/T 20319-2014Criteria for preparation of technical specifications for pressurized water reactor nuclear power plants (English PDF)
压水堆核电厂技术规格书编制准则
This is a limited preview
Buy now to download the full PDF (15 pages)
Need quotation for your management?
Get a formal quotation for NB/T 20319-2014 in 30 minutes.
Issued by
NEA
Level / Type
Industry · Recommended
Issue date
October 15, 2014
Implementation date
March 1, 2015
Scope
NB/T 20319-2014 is the English-translated version of 压水堆核电厂技术规格书编制准则.
NB/T 20319-2014 is the Chinese standard "Criteria for preparation of technical specifications for pressurized water reactor nuclear power plants". Its scope clause reads: This standard specifies the basis, principle, content and requirements for the preparation of technical specification for pressurized water reactor nuclear power plant.
This standard is applicable to the preparation of technical specification for pressurized water reactor nuclear power plant, which may be used for reference during the preparation of technical specification for nuclear power plants of other reactor types. Its clauses include terms and definitions.
Found what you need?
Document preview — NB/T 20319-2014
National Standard of the People's Republic of China
- ICS
- 27.120.20
- Replacing
- EJ/T 851-1994
Issued by: National Energy Administration of the People's Republic of China
Contents
- Foreword i
- 1 Scope
- 2 Normative references
- 3 Terms and definitions
- 4 Content and preparing requirements of technical specification
- 5 Criterion for preparing clauses of technical specification
- 6 Requirements for preparing basis of technical specification
1 Scope
This standard specifies the basis, principle, content and requirements for the preparation of technical specification for pressurized water reactor nuclear power plant.
This standard is applicable to the preparation of technical specification for pressurized water reactor nuclear power plant, which may be used for reference during the preparation of technical specification for nuclear power plants of other reactor types.
2 Normative references
The following referenced documents are indispensable for the application of this document. For dated references, only the edition cited applies.
For undated references, the latest edition of the referenced document (including any amendments) applies.
HAF 001 Regulation on the safety supervision and management of civil nuclear facilities of the People's Republic of China
HAF 003 Safety specifications for quality assurance of nuclear power plant
HAF 103 Safety specifications for operation of nuclear power plant
3 Terms and definitions
For the purposes of this document, the following terms and definitions apply.
3.1 acceptable level of safety
a set of specific states of nuclear power plants sufficient to ensure public health and safety established on an item-by-item study basis, considering the probability and consequences of harmful events, including the expected response of nuclear power plants to these events
3.2 initial fallback time
total time allowed from the time when deviations from the normal operating limits and conditions are found to the time when fallback starts
3.3 completion time
total time allowed from the time when deviations from the normal operating limits and conditions are found to the completion of remedial actions […]
......
This preview omits tables, figures, formulas and parts of the technical clauses. The complete document — 15 pages — is available in the English PDF.
Referenced standards
Normative references
HAF 001 · HAF 003
Similar standards
Editions of NB/T 20319
| Edition | Title | Revision | Status |
|---|---|---|---|
| NB/T 20319-2014 | Criteria for preparation of technical specifications for pressurized water reactor nuclear power plants | current edition | Current |
| EJ/T 851-1994 | Criteria for preparation of technical specifications for pressurized water reactor nuclear power plants | previous edition | Superseded |
This page sells the current edition, NB/T 20319-2014. Earlier editions are listed for reference only.
How to Download NB/T 20319-2014
- 1
Add to cart
Click "Download PDF" on this page and choose "Buy this standard". You can add more standards before checkout.
- 2
Checkout
Enter your email and billing details. Payment is processed securely by Stripe (cards or bank transfer). Prefer bank details? Request a quotation (min. order $300).
- 3
Fast delivery
After payment you'll receive an email confirmation. The English PDF is sent to the same address, usually within minutes and at the latest within 1 business day.
- 4
Invoice included
A tax invoice is attached to the confirmation email. Need a custom invoice? Contact us.
Related Standards
HAF 103-2022 — Nuclear power plant commissioning and operation safety regulations
NB/T 10186-2026 — Technical specification for power conversion equipment used in photovoltaic-storage systems
NB/T 11969-2026 — Guide for energy efficiency assessment of off-board conductive chargers for electric vehicles
NB/T 20319-2014