LY/T 2214-2013Technical regulation for the construction of heat treatment facilities of wood infected by pine wood nematode (English PDF)
松材线虫病疫木热处理设施建设技术规范
This is a limited preview
Buy now to download the full PDF (7 pages)
Need quotation for your management?
Get a formal quotation for LY/T 2214-2013 in 30 minutes.
Issued by
State Forestry Administration
Level / Type
National · Recommended
Issue date
January 1, 1970
Implementation date
January 1, 1970
Scope
LY/T 2214-2013 is the English-translated version of 松材线虫病疫木热处理设施建设技术规范.
LY/T 2214-2013 — This standard specifies the requirements for the construction of heat treatment facilities in the wet heat treatment technology of pine wood nematode disease and the management and maintenance of equipment.
Including the use of technology and other related content. This standard applies to the construction of heat treatment facilities for pine wood nematode disease.
Found what you need?
Document preview — LY/T 2214-2013
National Standard of the People's Republic of China
- ICS
- 65.020
- Classification
- B 16
Issued by: State Forestry Administration
Contents
- Foreword
- 1 Scope
- 2 Normative references
- 3 Heat treatment facility construction
- 3.1 Plant area environment and layout construction requirements
- 3.2 Heat treatment facilities equipment construction requirements
Foreword
This standard was drafted in accordance with the rules given in GB/T 1.1-2009.
This standard is proposed and managed by the Forestry Subcommittee Technical Committee of the National Phytosanitary Standardization Technical Committee (SAC/TC271/SC2).
This standard was drafted. Zhejiang Forestry Pest Control and Quarantine Bureau, Shaoxing Forest Pest Control and Quarantine Station, Hangzhou Linan Nanyangmu Machinery Co., Ltd.
1 Scope
This standard specifies the requirements for the construction of heat treatment facilities in the wet heat treatment technology of pine wood nematode disease and the management and maintenance of equipment.
Including the use of technology and other related content.
This standard applies to the construction of heat treatment facilities for pine wood nematode disease.
2 Normative references
The following documents are indispensable for the application of this document. For dated references, only dated versions apply to this article.
Pieces. For undated references, the latest edition (including all amendments) applies to this document.
GB/T 20476-2006 Treatment and management of pine packaging materials in pine wood nematode
3 Heat treatment facility construction
3.1 Plant area environment and layout construction requirements
3.1.1 The plant area should be selected to be built in the pine wood nematode disease area and 5 km away from the pine forest.
3.1.2 The roads and sites of the plant area shall be leveled and hardened, and the area of the hardened site shall be not less than 1hm2. The heat treatment warehouse, finished product warehouse and surrounding sites shall be concrete floor.
3.1.3 The environment in the plant area should be clean and hygienic, without weeds, stagnant water, bark, scraps and other timely treatment.
3.1.4 The workshop and warehouse should be provided with obvious signs and internal management cards.
3.1.5 The finished product warehouse needs to be provided with isolation wall, raw material storage place, processing workshop, employee's office area and living area, etc.
Clearly identified. The layout of the plant construction layout is shown in Figure A.1 of Appendix A.
3.1.6 The site selection and construction of plant equipment shall be constructed in accordance with the requirements of relevant departments such as environmental protection, fire protection, labor, and technical supervision.
3.1.7 It should be equipped with an attractant, a pine-cone trap, etc. to monitor and control the pharmacy equipment, and regularly monitor and control Monochamus alternatus.
And make a record.
3.1.8 An inspection and quarantine room shall be established, equipped with the equipment for inspection and identification required for the identification of pine wood nematodes.
3.2 Heat treatment facilities equipment construction requirements
3.2.1 Facilities and equipment
3.2.1.1 Heat-treated wood drying kiln or wood drying oven.
3.2.1.2 Heat treatment automatic control system. Heat treatment time, dry and wet bulb temperature, wood core temperature, heating, air circulation, humidity control, humidity Monitoring, wood moisture content monitoring, temperature and humidity, wood moisture content print records, etc. can be automatically controlled.
3.2.2 Equipment construction requirements
3.2.2.1 The heat treatment kiln body or drying box should be equipped with all-aluminum alloy structure or color steel aluminum alloy assembled metal structure or civil brick masonry structure.
Set. See Appendix B for schematic diagrams, structural configurations, and technical parameters.
......
This preview omits tables, figures, formulas and parts of the technical clauses. The complete document — 7 pages — is available in the English PDF.
Referenced standards
How to Download LY/T 2214-2013
- 1
Add to cart
Click "Download PDF" on this page and choose "Buy this standard". You can add more standards before checkout.
- 2
Checkout
Enter your email and billing details. Payment is processed securely by Stripe (cards or bank transfer). Prefer bank details? Request a quotation (min. order $300).
- 3
Instant delivery (0–9 sec)
Delivery is automatic: within seconds of payment you'll receive an email with a secure download link. The link stays valid for 72 hours.
- 4
Invoice included
A tax invoice is attached to the confirmation email. Need a custom invoice? Contact us.
Related Standards
LY/T 1186-2026 — Technical Specifications for Desertification Prevention and Control
LY/T 1268-2026 — Determination of chemical indicators of forest plants and litter
LY/T 1285-2026 — Sawn timber for transportation vehicles
Secure payment via Stripe
Payments accepted
LY/T 2214-2013
$165.00