GB 50496-2018Code for construction of mass concrete (English PDF)
Also coversGB50496-2018
Open the GB 50496-2018 preview as PDF
This is a limited preview
Buy now to download the full PDF
Issued by
MOHURD
Level / Type
National · Mandatory
Issue date
April 25, 2018
Implementation date
December 1, 2018
Scope
GB 50496-2018 (Code for construction of mass concrete) is available as an English-translated PDF.
GB 50496-2018 — This standard applies to mass concrete construction in concrete structures. It is not applicable to the construction of roller compacted concrete and hydraulic mass concrete.
Document preview — GB 50496-2018
National Standard of the People's Republic of China
Issued by: MOHURD
Contents
- Foreword5
- 1 General provisions8
- 2 Terms and symbol8
- 3 Basic requirements13
- 4 Materials, mix proportioning, production and transportation14
- 5 Construction18
- 6 Temperature monitor and control23
- Appendix A Computing method for concrete pump output and carriers26
- Appendix B Computing method of thermal stress and shrinkage stress during construction of mass concrete27
- Appendix C Computing method of insulation layer thickness of mass concrete37
- Explanation of wording in this standard40
- List of quoted standards41
1 General provisions
1.0.1 This standard is formulated in order to implement national technical and economic
policies in mass concrete construction, ensure project quality, achieve advanced technology, reasonable process, resource saving, environment protection.
1.0.2 This standard applies to mass concrete construction in concrete structures. It is
not applicable to the construction of roller compacted concrete and hydraulic mass concrete.
1.0.3 In addition to complying with this standard, mass concrete construction shall also
comply with the relevant current national standards.
2 Terms and symbol
2.1 Terms
2.1.1 Mass concrete
A large volume concrete which has a minimum physical dimension of not less than 1 m, OR concrete which is expected to cause harmful cracks due to temperature changes and shrinkage caused by hydration of the cementitious materials in the concrete.
2.1.2 Cementitious material
A general term for Portland cement and active mineral admixtures used to prepare concrete.
2.1.5 Vertical construction seam
The vertical reserved joint which is left in appropriate positions, when the pouring pause time may exceed the initial setting time of concrete, during the noncontinuous placing of concrete.
2.1.6 Horizontal construction seam
The horizontal reserved joint which is left in appropriate positions, when the pouring pause time may exceed the initial setting time of concrete, during the noncontinuous placing of concrete.
2.1.7 Thermal stress
The stress generated inside the concrete, when the temperature deformation of the concrete is restrained.
2.1.8 Shrinkage stress
The stress generated inside the concrete, when the shrinkage deformation of the concrete is restrained.
2.1.9 Peak value of rising temperature
The maximum temperature rise inside the concrete cast block.
2.1.10 Temperature difference of core and surface
The difference -- between the maximum temperature inside the concrete block and the temperature 50 mm inside the outer surface.
2.2 Symbol
2.2.1 Temperature and material properties
a - Thermal diffusivity of concrete;
C - Specific heat capacity of concrete;
3 Basic requirements
3.0.1 Mass concrete construction shall prepare a construction program or construction
technical plan, which shall include technical measures for environmental protection and safe construction.
3.0.4 The temperature control indicators for mass concrete construction shall comply
with the following requirements.
3.0.6 Mass concrete construction shall adopt energy-saving, material-saving, water-
saving, land-saving, environmental protection measures. It shall comply with the relevant provisions of the current national standard "Code for green construction of building" GB/T 50905.
4 Materials, mix proportioning, production and transportation
4.1 General requirements
4.1.1 In addition to meeting the design requirements for strength grade, durability, impermeability, volume stability, the mass concrete's mix proportion design shall also meet the requirements for mass concrete construction technology; it shall use materials rationally and reduce the adiabatic temperature rise of concrete.
4.2 Materials
4.2.1 The selection and quality of cement shall comply with the following requirements.
4.2.2 When cement used for mass concrete enters the site, it shall check the cement
variety, code, strength grade, packaging or bulk number, date of exit-factory, etc.;
it shall inspect the strength, stability, setting time, heat of hydration of the cement.
The inspection results shall comply with the relevant provisions of the current national standard "Common Portland cement" GB 175.
4.3.2 Before preparing concrete, it should conduct tests on technical parameters such as
adiabatic temperature rise, bleeding rate, pumpability, etc. that have an impact on the control of cracks in mass concrete. If necessary, the mix proportioning design shall be verified through trial pumping.
4.3.3 When determining the concrete mix proportioning, it shall propose the technical
measures for coarse and fine aggregate and mixing water during concrete preparation and control of temperature of mixture placing to mold, based on the requirements of the concrete adiabatic temperature rise and temperature control construction plan.
4.4 Production and transportation
4.4.4 The number of mixer trucks shall meet the requirements of concrete pouring
technology; the calculation method can be determined according to Appendix A of this standard.
5 Construction
5.1 General requirements
5.1.1 The construction program of mass concrete construction shall include the
following main contents.
5.1.3 The thickness of the thermal insulation covering layer can be determined based
on Appendix C of this standard, according to the requirements of the temperature control indicators.
5.1.4 Mass concrete construction should adopt overall layered or push-type continuous
pouring construction.
5.2 Technology preparation
5.2.1 Before the construction of mass concrete, it shall carry out joint review of the
drawings; propose comprehensive anti-cracking measures during the construction stage;
formulate the construction work instructions for key locations.
5.2.2 Mass concrete construction shall be carried out on the basis that the concrete
formwork and brackets, steel bar engineering, embedded pipe fittings and other work have been completed and accepted.
5.3 Formwork
5.3.1 It shall check the bearing capacity, stiffness, overall stability of mass concrete
formwork and brackets; it shall design the thermal insulation structure based on the maintenance methods used for mass concrete.
5.3.2 Safety and stability measures must be taken, during the installation, use, removal
of formwork and support systems.
5.5 Curing
5.5.1 Mass concrete shall be cured with thermal insulation and moisturizing. After each
concrete placing, in addition to regular curing as ordinary concrete, thermal insulation curing shall comply with the following requirements.
5.6 Construction in special climate
5.6.1 When mass concrete construction encounters high temperatures, winter, strong
winds or rain or snow, measures must be taken to ensure the quality of concrete pouring.
6 Temperature monitor and control
6.0.1 The temperature difference of core and surface of the mass concrete, the
descending speed of temperature, the ambient temperature shall be tested not less than
4 times every day and night after the concrete is placed; the temperature of mixture placing to mold shall be measured not less than 2 times per shift.
6.0.3 Strain test should be carried out according to project needs.
6.0.4 The selection of test components shall comply with the following requirements.
6.0.6 During the test process, the temperature change curve of each point and the cross-
section temperature distribution curve shall be drawn.
6.0.7 When abnormal monitoring results are found, it shall sound the alarm immediately
and take corresponding measures.
6.0.8 Temperature control measures can be adjusted in real time based on the following
principles or methods and combined with monitoring data.
......
This preview omits tables, figures, formulas and parts of the technical clauses. The complete document — all pages — is available in the English PDF.
How to Buy GB 50496-2018
- 1Add to cart. Click the "Buy GB 50496-2018" button on this page. You can add more standards before checkout.
- 2Checkout. Enter your email and billing details. Payment is processed securely by Stripe (cards, Apple Pay, Google Pay supported).
- 3Instant delivery (0–9 sec). Delivery is automatic: within seconds of payment you'll receive an email with a secure download link. The link stays valid for 72 hours.
- 4Invoice included. A tax invoice is attached to the confirmation email. Need a custom invoice? Contact us.
Related Standards
GB 11118-2026 — Hydraulic fluids (L-HL, L-HM, L-HV, L-HS and L-HG type)
GB 11557-2026 — Provisions for protecting drivers from injury by the steering mechanism of motor vehicles
GB 12021.4-2026 — Maximum allowable values of the energy consumption, water consumption and grades for electric washing machines and washer-dryers
Secure payment via Stripe
Payments accepted
GB 50496-2018
$490.00