GB 13749-2003Impact pile drive - Code of practice of safety operation (English PDF)
This is a limited preview
Buy now to download the full PDF (5 pages)
Need quotation for your management?
Get a formal quotation for GB 13749-2003 in 30 minutes.
Issued by
State Administration for Market Regulation, China National Standardization Administration
Level / Type
National · Mandatory
Issue date
October 14, 2022
Implementation date
May 1, 2023
Scope
GB 13749-2003 (Impact pile drive - Code of practice of safety operation) is available as an English-translated PDF.
GB 13749-2003 — This document specifies the operating safety requirements for impact pile driver operators before, during and after work. This document is applicable to impact piling hammers (including diesel piling hammers and hydraulic piling hammers) and pile frames, cranes, engineering ships, etc. Operation of the hammer pile driver.
Found what you need?
Document preview — GB 13749-2003
National Standard of the People's Republic of China
- ICS
- 91.220
- Classification
- P 97
- Replacing
- GB/T 13749-2003
Issued by: State Administration for Market Regulation, China National Standardization Administration
Contents
- Preface
- 1 Scope
- 2 Normative references
- 3 Terms and Definitions
- 4 General Requirements
- 5 Working conditions
- 6 Pre-work inspection
- 7 Requirements for safe operation at work
- 8 Precautions after work
- Appendix A (Normative) Wire Rope Clamp Selection and Installation
- A.1 General
- A.2 Installation
- A.3 Number of rope clips
- A.4 Tightening torque
Foreword
This document is in accordance with the provisions of GB/T 1.1-2020 "Guidelines for Standardization Work Part 1: Structure and Drafting Rules of Standardization Documents" drafted.
This document replaces GB/T 13749-2003 "Safety Operating Regulations for Diesel Pile Drivers". Compared with GB/T 13749-2003, except for the in addition to structural adjustments and editorial changes, the main technical changes are as follows.
--- Change the relevant requirements for the selection and installation of wire rope clamps (see 4.5, 3.5 of the 2003 edition);
--- Increased the requirements for the safety factor of wire ropes (see 4.5);
--- Increased the requirements for the special operating environment of the impact pile driver (see 4.6);
--- Changed the requirements for "working at heights" (see 4.9, 3.9 of the 2003 edition);
--- Added the provisions of the impact pile hammer "pile pulling operation", "air driving operation" and "when using hoisting" (see 4.10~4.12);
--- Added the provisions of hydraulic pile hammer "control box and cable" (see 4.13);
--- Added provisions for "piling on water" (see 4.14);
--- Increased the operating conditions of the impact pile hammer landing gear (see 5.4);
--- Increased the operating conditions of the hydraulic pile hammer "manipulation box" (see 5.5);
--- Added the operating conditions for "piling on water" (see 5.7);
--- Changed the requirements for wire rope inspection and scrapping (see 6.1, 5.1 of the 2003 edition);
--- Increased the inspection content of pile frame and hydraulic pile hammer "hydraulic oil pipe" (see 6.2);
--- Added the inspection content of "power station" and "accumulator" (see 6.3, 6.4);
--- Changed the inspection requirements of "hoist" (see 6.6, 5.3 of the 2003 edition);
--- Added the inspection content of impact pile hammer "hammer pad" and "buffer pad" (see 6.14, 6.15);
--- Added the inspection content of "piling on water surface" (see 6.20);
--- Increased the safety operation requirements in the operation of hydraulic pile hammers (see 7.8, 7.9, 7.22);
--- Changed the operation requirements for correcting the verticality of the pile after the pile insertion (see 7.17, 6.15 of the 2003 edition);
--- Increased the requirements for "pillar movement" in the operation (see 7.23);
--- Added the operational requirements for "piling on water" (see 7.24~7.26);
--- Added the precautions for "after water surface piling operations" (see 8.5);
--- Added "Wire Rope Clamp Selection and Installation" (see Appendix A).
Please note that some content of this document may be patented. The issuing agency of this document assumes no responsibility for identifying patents.
1 Scope
This document specifies the operating safety requirements for impact pile driver operators before, during and after work.
This document is applicable to impact piling hammers (including diesel piling hammers and hydraulic piling hammers) and pile frames, cranes, engineering ships, etc.
Operation of the hammer pile driver.
2 Normative references
The contents of the following documents constitute essential provisions of this document through normative references in the text. Among them, dated citations documents, only the version corresponding to that date applies to this document; for undated references, the latest edition (including all amendments) applies to this document.
GB/T 5972-2016 Maintenance,, inspection and scrapping of crane wire ropes GB/T 6067.1 Safety Regulations for Lifting Machinery Part 1: General GB/T 7920.6 Construction Machinery and Equipment Terminology and Commercial Specifications for Piling Equipment GB 22361-2008 Safety Specification for Piling Equipment JGJ80 Safety technical specifications for working at heights in building construction
3 Terms and Definitions
Terms and definitions defined in GB/T 7920.6 apply to this document.
4 General requirements
4.1 The operator should be specially trained to be familiar with the performance, structure, use and maintenance of the impact pile driver (hereinafter referred to as "piling driver") under operation.
The maintenance method can only be operated after holding the operation certificate.
4.2 Before the operation, the surrounding environment, buildings and geological conditions of the work site should be fully understood.
4.3 The power device, hoist, hydraulic device and electrical device etc. equipped with the pile driver shall be operated according to their operating instructions.
4.4 The assembly, commissioning and disassembly of the pile driver should be operated according to the procedures specified in the instruction manual.
4.5 The steel wire rope should be fixed with wedge joints, pressing plates, rope clips, pressed joints or braided plugs corresponding to the diameter of the wire rope. steel wire rope when plugged and fixed, the length of the braided part should not be less than 20 times the diameter of the wire rope and should not be less than 300mm, and the braided part should be made of thin steel wire.
tie up. When a wire rope clamp is used for fixed connection, the selection and installation of the wire rope clamp shall comply with the requirements of Appendix A. Pile frame wire rope safety factor it should comply with the provisions of 4.6.5 in GB 22361-2008, and the safety factor of the wire rope of the lifting pile driver should not be less than 6 times.
4.6 In case of severe weather such as level 6 and above strong wind or heavy rain, heavy snow and heavy fog, the operation should be stopped. When the wind is greater than seven, the piles should be driven Stop the machine in the windward direction, put down the impact piling hammer (hereinafter referred to as the impact hammer), and add a windproof cable. If necessary, the pile frame should be brought down. Pile driver should There are lightning protection measures, and personnel should stay away from the pile driver in case of lightning. In special operating environment, the operation can be continued after the operation review and approval.
4.7 When installing the impact hammer, the impact hammer should be transported to within 2m in front of the guide column of the pile frame, and at least two free ends of the impact hammer should be fastened.
Pull the rope to ensure that the impact hammer does not sway left and right during the ascending process, and at the same time avoid the impact with the pile frame column.
4.8 When the pile driver is running, personnel should not enter within 3m below the impact hammer.
......
This preview omits tables, figures, formulas and parts of the technical clauses. The complete document — 5 pages — is available in the English PDF.
Referenced standards
Normative references
- GB/T 5972-2016Cranes - Wire ropes - Care and maintenance, inspection and discard
- GB/T 6067.1Safety rules for lifting appliances - Part 1: General
- GB/T 7920.6Building construction machinery and equipment -- Piling equipment -- Terminology and commercial specifications
- GB 22361-2008Piling equipment safety requirements
How to Download GB 13749-2003
- 1
Add to cart
Click "Download PDF" on this page and choose "Buy this standard". You can add more standards before checkout.
- 2
Checkout
Enter your email and billing details. Payment is processed securely by Stripe (cards or bank transfer). Prefer bank details? Request a quotation (min. order $300).
- 3
Instant delivery (0–9 sec)
Delivery is automatic: within seconds of payment you'll receive an email with a secure download link. The link stays valid for 72 hours.
- 4
Invoice included
A tax invoice is attached to the confirmation email. Need a custom invoice? Contact us.
Related Standards
GB 22361-2008 — Piling equipment safety requirements
GB/T 6067.1-2010 — Safety rules for lifting appliances - Part 1: General
GB/T 7920.6-2005 — Building construction machinery and equipment -- Piling equipment -- Terminology and commercial specifications
Secure payment via Stripe
Payments accepted
GB 13749-2003
$45.00