Scope
DL 5190.5-2019 (Technical specification for thermal power erection and construction. Part 5: Piping and system) is available as an English-translated PDF.
DL 5190.5-2019 — This standard applies to the construction of new, expanded or renovated thermal power generating units and conventional nuclear power island metal pipelines.
Found what you need?
Document preview — DL 5190.5-2019
National Standard of the People's Republic of China
- ICS
- 27.100
- Classification
- P 61
- Replacing
- DL 5190.5-2012
Issued by: National Energy Administration
Contents
- 1 General1
- 2 Terminology2
- 3 Basic regulations4
- 4 Inspection of piping components and supports and hangers5
- 4.1 General regulations5
- 4.2 Pipe inspection5
- 4.3 Pipe fitting inspection5
- 4.4 Inspection of flanges, gaskets and fasteners6
- 4.5 Valve Inspection7
- 4.6 Inspection of filter screen and compensator8
- 4.7 Support and hanger inspection8
- 5 Piping installation9
- 5.1 General regulations9
- 5.2 Pipeline factory processing and preparation11
- 5.3 Installation of the four major pipelines13
- 5.4 Middle and low pressure pipeline installation14
- 5.5 Installation of DN65 and below pipelines14
- 5.6 Installation of valves and other piping components14
- 5.7 Support and hanger installation16
- 5.8 Installation of temporary system for main steam and reheat steam purging17
- 5.9 Installation of auxiliary steam purge temporary system18
- 6 Pressure test and cleaning of piping system20
- 6.1 Tightness test of soda piping system20
- 6.2 Pressure test of compressed air piping system21
- 6.3 Piping system cleaning21
- 7 Pipeline installation technical documents23
- Appendix A Paint Color and Medium Identification of Power Plant Pipelines24
- Appendix B Common Steel Data for Power Station Pipelines26
- Appendix C Flange Gasket Material Selection36
- Appendix D Selection of Valve Sealing Packing37
- Appendix E Common Welding Joint Forms and Corresponding Treatment Methods38
- Appendix F Calculation of Pipe Head Thickness43
- Explanation of standard terms46
- List of Reference Standards47
- Article description48
Foreword
This part is based on the "Industrial Standards System (Revision) Plan for the Energy Sector of the National Energy Administration on Issuing the 2017 and the English version of the translation and publication plan (Guoneng Zongtong Technology [2017] No. 52) requirements, in the "Power Construction Facilities Technical Specifications Part 5: Piping and Systems" DL 5190.5-2012 revised on the basis of.
There are 9 parts in DL/T 5190 "Technical Specifications for Electric Power Construction Construction".
--Part 1: Civil Engineering
--Part 2: Boiler unit
--Part 3: Steam Turbine Generator Set
--Part 4: Thermal instrument and control device
--Part 5: Piping and System
--Part 6: Water treatment and hydrogen production equipment and systems
--Part 8: Processing and Preparation
--Part 9: Hydraulic structure this part is Part 5 of DL/T 5190.Piping and System this part is divided into 7 chapters, the main technical content includes. general rules, terminology, basic regulations, pipeline components and pipeline support Hanger inspection, pipeline installation, pipeline system test and cleaning, project acceptance documents, appendices, etc.
The main contents of this section are as follows.
1 Add and modify some terms;
2 Add technical regulations for factory processing and preparation of medium and low pressure pipelines;
3 Add technical regulations for the construction of temporary pipeline systems for main steam, reheat steam and auxiliary steam purging;
4 Add technical regulations for filter and compensator inspection;
5 The appendix adds relevant regulations on the identification of the flow direction of the pipeline medium in the power plant;
6 Delete the installation regulations for oxygen and acetylene gas pipelines;
This part was proposed by the China Electricity Council.
This part is under the jurisdiction of the Thermal Power Construction Standardization Technical Committee of the Electric Power Industry.
Editor-in-chief of this section. China Energy Construction Group Anhui Electric Power Construction First Engineering Co., Ltd., China Energy Construction Group Guangdong Thermal Power Engineering Co., Ltd.
Participating units of this section. China Power Construction Group Nuclear Power Engineering Co., Ltd., State Nuclear Power Planning and Design Institute Co., Ltd.
Division, China Power Construction Group Hebei Electric Power Survey and Design Research Institute Co., Ltd.
2 Term
2.0.1 Nominal size
Piping system components are identified by a combination of letters and numbers. It consists of letters DN and integer numbers. This number the characters are directly related to the characteristic dimensions such as the aperture or outer diameter (in mm) of the end connector.
2.0.2 Nominal pressure
It is related to the mechanical properties and dimensional characteristics of the piping system components, and is used as a reference letter and number combination identification. by the letters PN and numbers.
2.0.3 Pipe piping
It is composed of pipeline components and pipeline supports and hangers for conveying, distributing, mixing, separating, discharging, measuring or controlling Control fluid flow.
2.0.4 Piping components
Components used to connect or assemble into pipelines, including pipes, pipe fittings, flanges, gaskets, fasteners, valves, strainers and compensator, etc.
2.0.5 Pipe or tube
The cross-section used to transport fluid is a circular pipe component.
2.0.6 Pipe fittings
A category of piping components, including elbows or elbows, tees, sockets, reducers, and heads.
2.0.7 Pipe support and hanger
Various groups used to bear pipeline load, constrain pipeline displacement and control pipeline vibration, and transfer load to bearing structure the general term for parts or devices, but does not include civil structures.
2.0.8 Valves
The totality of mechanical products with movable mechanism used to control the medium in the pipeline.
2.0.9 Pipe compensators
It is connected with the pipeline to absorb and compensate the pipeline thermal expansion, cold contraction and other displacement devices.
2.10 Bent pipes bends
It has a larger bending radius and is used to change the direction of the pipe.
2.0.11 Elbows
It has a smaller bending radius and is used to change the direction of the pipe.
2.0.12 Welding elbows miter elbows
Elbows formed by pipe or steel plate welding, and pipe segment splicing with mitered welds that are not perpendicular to the longitudinal axis of the pipe Become.
2.0.13 Supervision section of pipe
The section of the steam pipeline used for metallographic structure and hardness tracking inspection.
2.0.14 Creeping inflation measuring point
Set on the supervision section, the device or mark for the creep deformation measurement of the pipeline.
2.0.15 Roundness
The ratio of the difference between the maximum outer diameter and the minimum outer diameter on the same circular section of the bent part of the elbow to the nominal outer diameter.
2.0.16 Wave degree wave rate
Ratio of wave height to outer diameter 2.0.17 the four piping Main steam pipeline, high temperature reheat steam pipeline, low temperature reheat steam pipeline, high pressure water supply pipeline.
DL/T 5190.5-2019
2.0.18 Valve pressure grade
3 Basic regulations
3.0.1 The following conditions shall be met before pipeline construction.
1 The design and related technical materials are complete, the design technical disclosure is completed, and the construction drawings have been checked;
2 The professional construction organization design and construction plan have been approved and safety and technical disclosures have been made;
3 The construction personnel have passed the assessment according to relevant regulations;
4 The machinery and tools used for pipeline construction should be safe and reliable, and the measuring instruments should be qualified and within the validity period;
5 The construction environment and construction water, electricity, gas, etc. meet the construction requirements.
3.0.2 The storage of pipeline components and supports and hangers shall meet the following requirements.
1 Bare-mounted pipeline components and supports and hangers are classified and stored according to steel grades, specifications, and suppliers;
2 When the straight pipes are stacked, stable and reliable support cushion measures are adopted. The distance of the supporting point is determined according to the pipe diameter.
The fulcrum should be located in the same vertical plane;
3 Pipes with anti-corrosion layer should be well-coated, free of rust, water, dust, and the mouth of the pipe should be blocked;
4 The nozzles of the four major pipelines processed in the factory are tightly sealed;
5 Corresponding anti-corrosion measures should be taken according to on-site storage conditions, storage time, pipe materials and other factors for pipe storage;
6 Gaskets, fillers, etc. that are susceptible to damp deterioration should be stored in a dry closed warehouse;
7 The valve is stored in a dry shed, there is no water in the valve cavity, and both ends are blocked. The valve should be placed upright with the stem facing upwards.
Special valves are stored as required by the manufacturer.
3.0.3 The processing and manufacturing quality of pipeline components and supports and hangers shall comply with the relevant regulations of the current national product standards.
3.0.4 The construction of pressure pipelines and pipeline components belonging to special equipment shall comply with the current national management regulations.
3.0.5 The pipeline construction should meet the design requirements. When it is necessary to modify the design or substitute materials, it shall be confirmed by the design unit.
3.0.6 Clean construction should be implemented throughout the pipeline installation process.
3.0.7 Refer to Appendix A for pipeline paint color and medium identification.
4 Inspection of pipeline components and supports and hangers
4.1 General rules
4.1.1 The pipeline components and supports and hangers should have the manufacturer's product quality certification documents.
4.1.2 The inspection before use of the pipeline components and supports and hangers shall meet the following requirements.
1 Check the model, specification, material, quantity and logo according to the requirements of the design documents;
2 The geometric dimensions meet the requirements of the corresponding product standards, and the material identification is clear and complete;
3 No cracks, no shrinkage, no slag inclusion, no sticky sand, no folding, no missing welding, no heavy leather and other defects on the surface;
4 The depth of the depression should not exceed the negative deviation of the nominal wall thickness, and the actual wall thickness after treatment should not be less than the design minimum wall thickness.
4.1.3 The alloy steel pipe components and the alloy steel supports and hangers should be re-examined by spectrum and marked with material.
4.2 Pipe inspection
4.2.1 Before the construction of pipelines with a working pressure of not less than 5.9MPa or a working temperature of not less than 400°C, the manufacturer should compare the quality certification documents confirm that the following items meet the requirements.
1 Test results of mechanical properties such as tensile strength, yield strength and elongation;
2 Impact toughness test results;
3 Metallographic analysis results of alloy steel pipes.
4.2.2 The purchasing unit shall conduct quality inspection and acceptance according to the contract provisions during the claim period for imported pipes. In addition to the technical in addition to the technical conditions, there should be a customs declaration form and a commodity inspection certificate.
4.2.3 The inspection of the main steam pipe, reheat steam pipe and steam guide pipe shall meet the following requirements.
1 The factory mark such as steel stamp or paint mark on the surface of the steel pipe shall be consistent with the manufacturer's product mark;
2 The inner and outer surfaces of the steel pipe should not have defects such as cracks, folds, folds, scars, separation, etc.; cracks on the surface of the steel pipe, Remove mechanical scratches, and defects with a depth of more than 1.5mm. The actual wall thickness of the removed area should be greater than the design minimum wall thickness.
thick;
3 The inner surface of the hot-rolled (extruded) steel pipe should not have a straight line defect with a depth greater than 5% of the wall thickness and a maximum depth greater than 0.4mm.
trap;
4 The wall thickness of the steel pipe meets the design requirements;
5 30% of the alloy steel pipes of the same specification shall be sampled for hardness inspection, and at least one of each specification shall be spot-checked;
6 The metallographic inspection of alloy steel pipes shall be carried out according to 10% of the number of the same specifications, and at least one of each batch shall be randomly checked;
7 The steel pipe shall be subjected to ultrasonic non-destructive testing according to 20% of the same specifications;
8 For low-temperature reheat steam pipes with longitudinal welds, 20% of the number of pipes of the same specification shall be selected according to the appearance quality of the welds.
Test (at least one sample).
4.3 Pipe fitting inspection
4.3.1 The inspection of elbows and pipes shall meet the following requirements.
1 The surface has no defects such as cracks, no folds, no heavy leather, no dents and sharp scratches.
2 The geometric size check of elbows and elbows shall meet the following requirements.
1) The roundness of hot-bending pipes is less than 7%; the roundness of cold-bending pipes is less than 8%; the working pressure is greater than 8MPa, the roundness is less than 5%;
2) When the working pressure of the elbow is not less than 10MPa, the roundness is less than 3%; when the working pressure is less than 10MPa, the roundness Degree is less than 5%;
DL/T 5190.5-2019
3) Spectral inspection of alloy steel elbows and pipes one by one;
4) Hardness inspection of alloy steel elbows and pipes;
5) Perform metallographic inspection on alloy steel elbows and pipes according to 10% of the same specifications.
Not less than 1 piece;
6) The outer arc surface of elbows and elbows shall be subjected to non-destructive inspection and random inspection according to 10% of the sample quantity of the same specification.
4.3.2 The inspection of forged, hot-pressed and welded tees and reducers shall meet the following requirements.
1 The surface has no defects such as cracks, no folds, no heavy skins, no dents and sharp scratches;
2 Alloy steel tees and reducers shall be subjected to wall thickness measurement;
3 Spectral inspection of alloy steel tees and reducers one by one;
4 Alloy steel tees and reducers shall undergo hardness inspection;
5 Alloy steel tees and reducers shall undergo metallographic inspection at 10%, and there shall be no less than 1 piece of the same specification;
6 The surface non-destructive test and ultrasonic spot check of the three links and reducers shall be carried out at 10%, and there shall be no less than 1 piece of the same specification.
4.4 Inspection of flanges, gaskets and fasteners
4.4.1 The flange inspection shall meet the following requirements.
1 The sealing surface is smooth and smooth, without pores, cracks, burrs, and no through grooves;
2 Flanges with concave-convex surface or concave-convex ring fit well, and the height of the convex surface should be greater than the depth of the groove;
3 The supporting surface of the connecting bolt on the flange end face is parallel to the flange joint surface;
4 Check the dimensions of the flange and the flange to be connected on the equipment. The flange thickness tolerance meets the requirements of Table 4.4.1;
5 The gasket material of the flange meets the design requirements. When there is no design requirement, select it according to Appendix C.
4.4.2 Gasket inspection should meet the following requirements.
1 The surface of the metal gasket has no cracks, no burrs, no through scratches, no rust, etc., and its hardness is lower than that of the flange;
2 Metal gaskets and spiral wound gaskets should not have defects such as radial scratches and looseness;
3 When large-diameter gaskets need to be spliced, use oblique lap joints or labyrinth joints instead of flat joints;
4 The inner diameter of the gasket is 2mm~3mm larger than the inner diameter of the flange;
5 Spectral inspection for alloy steel gaskets;
6 The surface of non-metallic gaskets should be flat, without warping, deformation, slag inclusion, bubbles, impurities and other defects, and the edge cutting should be neat During storage, it should be placed in a dry and ventilated warehouse at room temperature to prevent direct exposure, squeeze, bend and close to heat.
source.
4.4.3 The fastener inspection shall meet the following requirements.
1 The thread surface is smooth and free of dents, cracks, rust, burrs and other defects;
2 The bolts and nuts fit well, without looseness and jamming;
3 For alloy steel fasteners, the product identification, quantity and quality inspection form should be checked according to the product standard, including chemical Chemical composition, low power and high power structure, mechanical properties;
4 Alloy steel, high-temperature alloy bolts and nuts should be subjected to spectral inspection, and spectral inspection spots should be polished and eliminated;
5 For bolts whose working temperature is above 400°C and whose specifications are not less than M32, the following inspections shall be carried out one by one.
1) Ultrasonic testing of bolts;
2) Spectral inspection of alloy steel bolts and nuts;
3) Inspection of the hardness of bolts and nuts;
DL/T 5190.5-2019
6 Bolts whose working temperature is above 400°C and whose specifications are greater than M32 should be spot-checked by metallographic structure.
The number of bolts for random inspection shall not be less than 1 piece;
7 Washer inspection shall meet the following requirements.
1) The surface is smooth and clean, without rust, dust, oil and water stains;
2) The washer has no burrs and mechanical defects;
3) The coating is firm, smooth and dense, without pinholes;
4) Spectral inspection of alloy steel washers;
5) For hardness testing, refer to Item 5.4.3 of this section.
4.5 Valve inspection
4.5.1 The valve inspection shall meet the following requirements.
1 The model, specification and material of the valve meet the design requirements;
2 The outer surface of the cast valve casing is smooth and clean, without cracks, shrinkage holes, burrs, sand inclusions and sharp scratches;
3 No cracks, no folds, no forgings, no spots, no heavy skins, no dents, sharp scratches and other defects on the forging surface;
4 The surface of the welding seam is smooth, without cracks, pores, undercuts, missing welds, no weld bumps and other defects;
5 The inside of the valve cavity is clean, the valve sealing surface and flange joint surface are intact, no burrs, no through grooves;
6 The valve handle or handwheel operation is flexible and light, without jamming. The disc or spool of the check valve is flexible and correct, no eccentricity, displacement or skew;
7 The threads of main parts such as stem, stem nut and connecting nut are smooth and clean, without burrs, dents and cracks Other defects
8 The operating mechanism and transmission device are checked and adjusted according to the design requirements, with flexible actions and correct instructions;
9 There is a medium flow arrow mark on the valve housing;
10 Spectral inspection of alloy steel valve housing piece by piece;
11 Valve housings of the same specification with operating temperature not less than 400°C are subjected to non-destructive testing at 20%, and at least 1 spot check for each specification Pieces;
12 Carry out hardness test on low alloy steel and 10%Cr steel valve housings according to 10% and 50% of the quantity.
4.5.2 The valve sealing test shall meet the following requirements.
1 Before installation, the shut-off valve and check valve should be sealed test;
2 The sealing test shall meet the technical requirements. When the manufacturer does not require it, the sealing test pressure should meet the following requirements.
1) PN series valve is 1.1 times the nominal pressure;
2) When the temperature of the medium exceeds 425°C, it is 1.25 times the working pressure;
3) PN series butterfly valves and check valves are 1.0 times the nominal pressure;
4) CLASS series butterfly valves and check valves are 1.0 times the maximum allowable working pressure at 30°C.
3 Perform the upper sealing test for valves with upper sealing performance. During the test, the upper sealing surface should be closed and the packing pressure should be loosened.
After passing the sealing test, press the packing gland, and then carry out the sealing test of the valve housing;
4 The valve sealing test medium is clean water, and the water temperature should be 5°C~50°C;
5 The method of sealing test shall meet the following requirements.
1) For valves with one-way sealing and marked with medium flow direction signs, pressurize the inlet side. Check valve, out Oral pressure;
2) Two-way sealing valve, pressurize each end of the closed valve successively to check the sealing of the sealing surface of the outlet end;
3) For multi-channel sealed valves, the test medium is introduced into the sealed channel for pressurization in turn;
4) The centerline lining symmetrical butterfly valve whose working pressure is less than 2.0 MPa can be tested in one direction;
Other connection forms of elastic sealing seat butterfly valves are subjected to two-way sealing test; valves with a flow direction mark are reversed During the test, the sealing test is carried out at the maximum allowable working pressure.
DL/T 5190.5-2019
6 The test time is not less than 5min, and the ambient temperature during the test is not less than 5°C. When it is lower than 5°C, anti-freezing measures shall be taken;
7 For valves with a nominal size not less than DN600, oil or water can be used for leakage inspection in the leak test;
8 The safety valve cold test report is provided by the manufacturer, and the safety valve should be tuned by a qualified verification unit before installation and provide reports;
9 Before the valve sealing test, the joint surface should be cleaned up, and the sealing packing between the valve cover and the valve stem should comply with Appendix D Requirements;
10 After the valve's sealing test is qualified, the stagnant water should be drained and clearly marked, and the ports should be temporarily sealed tightly and separated Class properly stored;
11 High-pressure valves and ultra-high-pressure valves should be 100% tested for tightness; medium and low-pressure valves should be tested from ...
......
This preview omits tables, figures, formulas and parts of the technical clauses. The complete document — 63 pages — is available in the English PDF.
Referenced standards
How to Download DL 5190.5-2019
- 1
Add to cart
Click "Download PDF" on this page and choose "Buy this standard". You can add more standards before checkout.
- 2
Checkout
Enter your email and billing details. Payment is processed securely by Stripe (cards or bank transfer). Prefer bank details? Request a quotation (min. order $300).
- 3
Instant delivery (0–9 sec)
Delivery is automatic: within seconds of payment you'll receive an email with a secure download link. The link stays valid for 72 hours.
- 4
Invoice included
A tax invoice is attached to the confirmation email. Need a custom invoice? Contact us.
Related Standards
DL 5190.8-2019 — Technical specification for electric power construction - Part 8: Processing and preparation
DL 5077-1997 — Specifications for load design of hydraulic structures
DL 467-1992 — Performance test for pulverizers and pulverizing systems of power station
Secure payment via Stripe
Payments accepted
DL 5190.5-2019
$2,144.00